Restoration and Renewal of the Palace of Westminster
House of Commons, 25 November 2026.
Nusrat Ghani (Conservative, Sussex Weald)
I inform the House that Mr Speaker has selected the amendment in the name of the Prime Minister.
I call the shadow Leader of the House.
Jesse Norman (Conservative, Hereford and South Herefordshire)
I beg to move,
That this House expresses grave concern at the enormous projected costs of the Restoration and Renewal Programme, estimated at between £11.1 billion and £39.2 billion; believes that the scale of expenditure contemplated is particularly difficult to justify given the severe pressure on public finances; recognises the urgent need to address serious deficiencies in the Palace of Westminster’s fabric, infrastructure and fire safety, while expressing concern at the absence of an agreed budget or affordable scope of works to do so and the continuing failure to establish effective governance, financial control and accountability; and questions the assumptions underlying the proposals for the extensive decant of Parliament, the resulting disruption to parliamentary proceedings and the substantial additional costs involved.
This, as the House will be aware, is nominally an Opposition day debate. However, the motion stands first in my name, and, on the Opposition Benches, it is subject to a free vote. It is, it must be said, a rather unusual procedure, but we have been forced to it by the Government’s unwillingness to act over the past nine months on the restoration and renewal of the Palace of Westminster.
The R and R client board published its costed proposals document on 5 February. Since then, the Government, who control the business of the House, have done nothing about it. That is nine whole months. You will be pleased to know, Madam Deputy Speaker, that I have just seen that we have been successful: the Government have at last published their motion, just a few minutes ago. I am delighted by that fact. [Interruption.] The Leader of the House, who is grumbling somewhat from a sedentary position, may try to decry this debate as an attempt to make this piece of House business party political—[Interruption.] Thank you. He may criticise our call to do the necessary work at a far lower cost as a needless further delay, but the opposite is true.
My colleagues can vote as they wish on this motion.
I hope that all Members of this House will be allowed to do so by their Whips at the end of this debate. I ask the Leader of the House to confirm that Labour will not be whipping its own Members on this House business and that all Members will be able to speak when the motion comes before the House.
The truth is that this delay has been caused by the Government’s absolute unwillingness to act. I have asked time and again from the Dispatch Box for them to publish a motion, but far from approaching this issue in a cross-party way, they have done the exact opposite. They have offered no debate, no engagement, no attempt to bring colleagues together. If there is any urgent safety work to be done now, the Government have had two-and-a-half years in which to amend the legislation and get it done, so I ask the Leader of the House again what the reason has been for this delay.
It seems that the Government’s goal is to leave this business to a quiet day long after the Budget, perhaps on a one-line Whip, and push through this House a £3 billion spend—that is just the initial spend—after a single, short debate and the thinnest possible scrutiny by this Chamber. Now they offer the weakest of amendments in response to our motion today.
Gareth Snell (Labour/Co-operative, Stoke-on-Trent Central)
I remember debating this when I was in the House in 2017—obviously there were a number of Conservative Governments in that subsequent period who did not bring forward a resolution. The right hon. Gentleman’s motion sets out the things he disagrees with and what he thinks the cost will be. At what point will he publish his alternative measure so that if we do support this motion today, we know what we are likely to back?
Jesse Norman (Conservative, Hereford and South Herefordshire)
I am grateful to the hon. Gentleman for his intervention, but he is very sadly misinformed. He seems to have forgotten that the Government brought a motion forward in 2019 on restoration and renewal. As regards my own views, they have been extensively published, but I will come to them in due course.
As I was saying, the amendment that the Government have offered is, I am afraid, astoundingly weak. The cost of the Government’s nine-month delay this year has been estimated by the Public Accounts Committee to be between £220 million and £290 million. The Government own this cost and those nine months. It would be disingenuous in the extreme for them to now push ahead on this wildly expensive project with no serious scrutiny, no genuine accountability and no political consensus, either in this House or between the Houses. Indeed, as experience has shown time and again, it would be an act of extreme folly. No one disputes that the Palace of Westminster needs restoration; the question is at what cost.
Richard Tice (Reform UK, Boston and Skegness)
Isn’t the problem that nobody can justify spending somewhere between £10 billion and £40 billion on repairing this great place? The issue is that the brief is wrong, because there is not one, not two, not three but four boards of governance. That is one of the first problems.
Jesse Norman (Conservative, Hereford and South Herefordshire)
I thank the hon. Gentleman for his remarks. Knowing that he will have closely scrutinised the costed proposals report, I am sure he will have seen that the proposal is now to add another board in relation to the client board and the programme board following passage of the motion. That would be a further catastrophic downgrading of the very little accountability that presently exists.
Jerome Mayhew (Conservative, Broadland and Fakenham)
Will my right hon. Friend give way?
Jesse Norman (Conservative, Hereford and South Herefordshire)
If I may, I will make a bit more progress.
If a Department proposed to spend up to £40 billion on restoring a single building without an agreed budget, settled scope, clear political leadership or accountability to Ministers, Parliament would vigorously object, but this is precisely the situation that Parliament now finds itself in. The costed proposals report, as has been mentioned, gives a range of £11 billion to £39 billion in projected cost. These figures are estimates, I would emphasise. There is no budget as such here. These are not contractual commitments or guaranteed upper limits, and they are eye-watering sums.
Moreover, they are being proposed without the normal disciplines of ministerial responsibility, Treasury oversight and departmental accountability applied to major governmental infrastructure projects. Given the history of British infrastructure mega-projects, it is not hard to foresee scope for massive further cost inflation.
Anna Dixon (Labour, Shipley)
As a member of the Public Accounts Committee, which has scrutinised the proposals in some detail, along with many other historical infrastructure projects, I am surprised that the right hon. Gentleman and his party seem to be ignoring the Committee’s recommendations that Members now have plenty of information to make a decision and that it is vital that we get on and start with this project as soon as possible.
Jesse Norman (Conservative, Hereford and South Herefordshire)
I am afraid to say that I did not think that the Public Accounts Committee showed itself at its best in that report. We did not see, for example, anything like the detailed scrutiny of individual costs that I would have expected. I will come on in a second to the costings, then the hon. Lady can decide whether the PAC has done its job in relation to those.
It is easy to get lost in such enormous numbers, but what do they mean in real terms? By way of comparison, the cost of the restoration of Notre-Dame was about £600 million. Yes, it has just a quarter of the footprint of the Palace of Westminster and was not occupied during its restoration, but as one commentator remarked, we could restore a Notre-Dame every single week over a year for the cost of one R and R and still have enough cash left over for a nuclear-powered aircraft carrier.
Marie Goldman (Liberal Democrat, Chelmsford)
I wonder whether the right hon. Gentleman would like to check his figures. He just said that Notre-Dame has a quarter of the footprint of the Palace of Westminster. I believe Notre-Dame to have a floorspace of 5% of the Palace of Westminster, making it one twentieth of the size. Would he like to correct the record?
Jesse Norman (Conservative, Hereford and South Herefordshire)
Of course, it has never been known for the Liberal Democrats to indulge in equivocation. The hon. Lady has shifted the argument from the footprint to the floorspace. The footprint is a quarter of the size, and that is what I described.
What else could £40 billion pay for? We could have 40 major new hospitals up and down the country, 50 new Wembley stadiums, and new Elizabeth lines in two large cities, perhaps in and around Birmingham or linking Manchester and Liverpool. We could pay for the standing military aid of this country to Ukraine for 13 more years to defend the security of Europe. It would amount to £1,400 for every household in this country, and if one were to spend one pound every second on R and R, it would take nearly 1,270 years to spend £40 billion. That is how large that number is.
Let us be clear: spending this gigantic sum on a single building would be the utmost folly, but still more when the national debt is hovering near 100% of GDP and the public finances are so tight. The cost is so high that the Office for Budget Responsibility will need to include in its forecasts. Every Member of this House will have to account at the next election for their vote on this matter today. When their constituents ask where the money is for potholes, social housing or defence, they will have to explain why so much was overspent on a single building.
We might feel more confidence if the parliamentary authorities had a good track record of managing infrastructure projects, but I am afraid that the reverse is true. The new security fence outside St Stephen’s gate has been widely criticised for its ugliness and cost. The Lord Speaker rightly described the new £10 million entrance to the House of Lords as
“a complete white elephant and a disaster”.
The procurement to restore the Victoria Tower failed and had to be redone. The doors in Portcullis House were not disability-friendly even when it was built. Today the atrium roof leaks and is swathed in unsightly protective wrapping and needs replacing just 25 years after it was installed. These are not reassuring precedents.
Julian Lewis (Conservative, New Forest East)
One thing I think we need to get clear is what is the primary purpose of this restoration. Is it fundamentally just to make the building safe or is it to try and in some way transform the building? According to the National Audit Office’s June 2026 update report, it is the former. It says:
“The Palace requires extensive restoration to address serious risks and priority improvements, including deteriorating mechanical and electrical systems, fire safety issues, the presence of asbestos and the condition of the historic fabric.”
Why should it take £40 billion just to do repairs?
Jesse Norman (Conservative, Hereford and South Herefordshire)
I thank my right hon. Friend for his question. Of course, it should not. My whole point has been that we should focus on restoration and the vital safety, security and wellbeing work that is required and mentioned by the NAO, but not on other aspects of the project that push up its costs as much as they are doing.
Christopher Vince (Labour/Co-operative, Harlow)
Will the right hon. Member give way?
Jesse Norman (Conservative, Hereford and South Herefordshire)
No. If I may, I will keep pushing on.
The recent precedents from construction around the House of Commons and the House of Lords are not reassuring. Instead, let us look at the restoration of Buckingham Palace. The NAO has praised its disciplined management, risk controls and willingness to make practical trade-offs. The palace has remained operational throughout, with Her late Majesty the Queen in residence there in her final years. That project has a budget of £389 million, which is less than 1% of the potential cost of R and R. Can any sane person think R and R makes sense in the face of that comparison?
Buckingham Palace also shows us a better way. Successful restoration requires a good client, clear accountability, tightly defined objectives and competent execution. R and R presently lacks the political consensus it needs both within this House and in the two Houses as a whole. When it fails, as it surely must, Parliament will need a fall-back.
Here is my suggestion. Parliament should immediately commission a rapid, independent red team review of the entire proposition. That 90-day exercise should bring together existing engineering assessments, cost estimates, procurement plans and safety requirements and subject them to rigorous challenge. It should be run by a small team under the joint leadership of the two Speakers, with explicit cross-party support in both Houses and a clear mandate to distinguish essential health and safety works—the point made by my right hon. Friend the Member for New Forest East (Sir Julian Lewis)—from discretionary enhancements. Its objective should be to put before Parliament a clear budget, scope and schedule for a scaled-back programme, focusing on the primary job of restoration. Some temporary decanting may be unavoidable, but only as justified by engineering necessity.
Christopher Vince (Labour/Co-operative, Harlow)
I thank the shadow Leader of the House for taking an intervention—I promise that it is a friendly one. He is a good friend of my predecessor in this place. Does he recognise that, as well as the health and safety aspects he mentioned, we should think about enhancements to make the place more accessible for people with disabilities?
Jesse Norman (Conservative, Hereford and South Herefordshire)
I very much agree with that. We have already done good work, led by the Leader of the House, on the Modernisation Committee in relation to disability improvements across the Palace.
Before I close, let me address the Government’s amendment. It is remarkably weak. Nobody disputes the responsibility to protect the Palace of Westminster; the questions are how, at what cost, over what period and under whose supervision? R and R has always been a parliamentary programme, not a Government programme. In that spirit, the previous Conservative Government passed the Parliamentary Buildings (Restoration and Renewal) Act 2019. The motion before us is not a partisan one. It does not blame the Labour party for what has always been House business, but it presses the Government on the delay and lack of scrutiny. Only the Government can remedy that failure. At last, they have done so by publishing their motion.
The Government’s amendment implies that the Opposition are seeking to delay essential safety works; that is not true. Every Member of the House believes that remediation should continue. The Government have had 2.5 years to make it so.
The Government’s amendment presents no evidence that a more focused programme could not deliver safety improvements still more rapidly than is being contemplated. It contains no recognition of the pressure on the public finances of the national debt or the cost of servicing it. As for its claim about jobs, any infrastructure project of tens of billions of pounds would support thousands of jobs—that is not a test of value for money. In comparison, High Speed 2 is expected to support 34,000 construction jobs and no one thinks that HS2 will be good value for money. Many more jobs and much more growth would be created if that money were better spent.
Finally, the amendment makes the extraordinary claim that
“the phase one works will deliver value for money for the taxpayer by capping initial costs”.
That is economically illiterate. Capping initial costs is not the same as capping final costs. A spending cap is not evidence of value for money, and the amendment offers no comfort on that issue, on scope, on schedule or on accountability; nor does it offer any justification for why Parliament should exempt itself from the financial disciplines that it seeks to apply to other public bodies.
The Government’s amendment is an insult to the Commons. It would be folly to proceed with R and R on that basis, especially when better models exist. I commend the motion to the House.
Alan Campbell (Labour, Tynemouth)
I beg to move an amendment, to leave out from “House” to the end of the Question and add:
“recognises that it has a responsibility to repair, secure and protect the Palace of Westminster, part of a UNESCO World Heritage Site of global historic and symbolic significance, for future generations; notes the previous Government’s failure to support Parliament in implementing a credible Restoration and Renewal Programme in 14 years; further notes that this indecision has added significant costs to the remediation required and that further delay would only increase costs and risk catastrophic failure of the buildings, putting the safety of those who work on and visit the parliamentary estate at risk; also notes the National Audit Office Report, Restoration and Renewal of the Palace of Westminster: 2026 Update, HC 32, and the 19th Report of the Committee of Public Accounts, Restoration and Renewal of Parliament: Costing and governance, HC 90, which recommended proceeding immediately with works; notes that the Restoration and Renewal Programme will support thousands of jobs across the country; further notes that the phase one works will deliver value for money for the taxpayer by capping initial costs; and supports the Government’s commitment to table a motion for debate so that individual hon. Members can take a decision in a proper and informed way before the end of the year.”
It is entirely a matter for the Opposition what they choose to debate on their Opposition day, but I have to say that their choice today is both disappointing and, frankly, odd. It is disappointing because the Opposition knew full well that the Government intended to provide time for a debate on restoration and renewal before Christmas. The shadow Leader of the House had seen a draft motion.
Jesse Norman (Conservative, Hereford and South Herefordshire)
No, that is not correct.
Alan Campbell (Labour, Tynemouth)
It is true. [Interruption.] That is absolutely true. I gave it to you some weeks ago.
Nusrat Ghani (Conservative, Sussex Weald)
Order. The Leader of the House is very experienced. There should be no “you” or “yours”, and no secondary debates when a debate is already taking place here in the Chamber.
Alan Campbell (Labour, Tynemouth)
Thank you, Madam Deputy Speaker. What has happened with that motion is that I tried—we tried—to build consensus around the approach on this matter. As the right hon. Gentleman has said, it is not a Government project; it is a parliamentary project, and in my view any progress needs to be sustainable.
Alison Griffiths (Conservative, Bognor Regis and Littlehampton)
I thank the Leader of the House for being so generous in giving way. Last year, along with probably most of the MPs in the Chamber, I went on an R and R tour of Parliament. At that time, we were presented with three choices, and there was a middle ground, which to me seemed extremely sensible. I have yet to hear a good answer as to why that middle ground has been removed from the final options. We are being given a binary choice between something that is incredibly expensive and—well, actually both are incredibly expensive.
Alan Campbell (Labour, Tynemouth)
I will get to that point in a moment, as I want to say something about costs and about choices, but this is a matter not just of choices but of when those choices will be exercised.
My intention was to give the right hon. Member for Hereford and South Herefordshire (Jesse Norman) and the House the courtesy of announcing the debate in the business statement tomorrow, but instead it seems that he has preferred to jump the gun. It is odd, because most Opposition parties would make the case to the Government of the day that they have so much to say and so little time in this place to say it, with just 17 Opposition days. This Opposition seem to have the opposite problem: they have got too much time and nothing much to say.
The Opposition’s motion is sadly predictable. It sums up Conservative party policy over the last 14 years in a nutshell: identify a problem, say how bad it is and then run away from making a decision. We saw that in its approach to health, defence, education and all other matters, and that approach is reflected in the motion before us.
In 2017, the then Deputy Leader of the House, Sir Michael Ellis—a man I hugely admired, who is missed in this place—said:
“We have reached a point where make-do-and-mend is simply not an option.”
He also said that
“we cannot pass the buck any longer.”—[Official Report, 25 January 2017; Vol. 620, c. 117WH-118WH.]
Yet here we are, nearly 10 years later, with a motion that seeks to pass the buck.
In 2020, the then Leader of the House, Sir Jacob Rees-Mogg, said, rightly, that
“if we fail to act, the building risks being lost to history forever.”—[Official Report, 16 July 2020; Vol. 678, c. 1736.]
A year later, he said:
“The work needs to be done, and it needs to be done as soon as is practicable.”—[Official Report, 20 May 2021; Vol. 695, c. 958.]
But he then went on to warn against hurrying along in an over-hasty fashion.
In 2022, the then Leader of the House Sir Mark Spencer said:
“The building needs to be repaired”,
but he then asked,
“why are we here again?”—[Official Report, 12 July 2022; Vol. 718, c. 272-272.]
That is a very good question.
Anna Dixon (Labour, Shipley)
My right hon. Friend is clearly setting out the dither and delay from the Conservative party. Does he recognise that it has been seven years since the passing of the 2019 Act, which the shadow Leader of the House mentioned, and that in that time the building has become even more unsafe? We do not want a Notre-Dame. We do not want to wait for the building to burn down. Does my right hon. Friend agree that the time for reviews and further diagnosis is over? Does he agree with the Public Accounts Committee that we need to get on and make the decision?
Alan Campbell (Labour, Tynemouth)
I absolutely agree. One problem with the speech of the shadow Leader of the House was that it suggested not a single solution apart from applying the brakes. I listened carefully to what he said today. I have heard on the airwaves and have read in the newspapers over recent weeks his calls for the programme to be paused and reviewed. He even likened it to a runaway train. It is the only runaway train that has yet to leave the station.
I fully appreciate the real anxieties caused by the costs associated with the programme. However, the reality is that the hope for a cheaper, less disruptive solution and a delay until we find one is a message that we have heard over and over again. The only thing we know is that it gets us no further and only increases cost and risk. We are approaching a fundamental question that has loomed over this House for more than a decade. We are the current custodians of the seat of British democracy. We need to fulfil our duty to preserve and restore the Palace of Westminster. As the shadow Leader of the House’s predecessors have said, and as I have quoted, we cannot allow this iconic building to fall victim to catastrophic failure on our watch because we are too hesitant to put into action the advice and the expertise of every independent review that this House has ever sought.
Wendy Morton (Conservative, Aldridge-Brownhills)
The Leader of the House talks a lot about our democratic duty, but he fails to mention our duty as legislators and parliamentarians to take account of the public purse. Does he agree that, at the end of the day, it is taxpayers’ money that he seeks to spend?
Alan Campbell (Labour, Tynemouth)
We are the custodians of the public purse. I am not arguing that there should be any amount of money available. There are ways in which we can look at what needs to be spent and make sure that we get value for money. However, when the right hon. Lady is next on the radio, having been sent out by her Front Benchers to do the 8.10 am slot on Radio 4, and she wants to talk about some foreign affairs issue of the day, I can guarantee that at some point, if she is not careful, she will not get that question about foreign affairs, because for the first 20 minutes she will be asked, “How did you allow the House to burn to the ground?” That is the risk we run.
Wendy Morton (Conservative, Aldridge-Brownhills)
rose—
Alan Campbell (Labour, Tynemouth)
No, no. The right hon. Lady has had her go.
As all the shadow Leader’s predecessors have said, and as I have quoted, we cannot allow this building to fall victim to catastrophe.
Julian Lewis (Conservative, New Forest East)
Let me start with an admission: the Leader of the House knows far more than I do about this issue and the detail. What I cannot understand, however, is how the PAC report can come up with figures like this:
“each year of delay adds up to £420 million to the potential lifetime cost of delivering the Programme.”
We are all agreed that we do not want a catastrophic event, but how can it cost billions and billions to stop the place burning down? It is just nonsense.
Alan Campbell (Labour, Tynemouth)
Because the right hon. Gentleman takes an interest in these matters, he may well have been in the debate at which the then Leader of the House Andrea Leadsom addressed that point. She talked about the cost of delay in terms of the sticking-plaster approach, which we still have. She also talked about the billion pounds of neglect that is not being addressed by a sticking-plaster. That bill is only going up. The right hon. Gentleman knows, from his constituency and from every constituency, that the cost of repair and restoration will not come down over the years. It will go up.
John McDonnell (Labour, Hayes and Harlington)
Members need to take into account the fact that this is a workplace. There are 3,000 workers who work here. They have had to endure asbestos. Some have to have their health monitored for the rest of their life. There have been floods, electrical faults and, to be frank, working conditions that are just unacceptable in the 21st century. We have a responsibility to those workers, and every single trade union representing them has made it clear that they do not wish any further delay in the refurbishment and restoration of this building.
Alan Campbell (Labour, Tynemouth)
I am grateful to my right hon. Friend, who speaks a great deal of sense on these matters. On these occasions, we tend to think about the 650 Members of Parliament whose right it is to turn up at this building, but what about the thousands of people who work here, along with the hundreds of thousands of visitors who come into this place?
Peter Prinsley (Labour, Bury St Edmunds and Stowmarket)
I should like to report that in the summer, the second floor of 53 Parliament Street had a complete failure of air conditioning and my staff were overheated, working illegally. There is now a complete failure of central heating, so my staff are completely freezing. I echo what my right hon. Friend the Member for Hayes and Harlington (John McDonnell) says about the conditions for our workers.
Alan Campbell (Labour, Tynemouth)
As ever, my hon. Friend makes a sensible case. What he describes is far too typical, not just in that building but in this one.
The shadow Leader of the House wishes to criticise me and the Government for a lack of progress on the costed proposals before now. I remind the House that the report was published in February this year, following years of engagement and analysis. The National Audit Office considered costings and governance in its June report, which was followed by a report from the Public Accounts Committee earlier this month. The Public Accounts Committee report builds on the NAO report and two public evidence sessions. Any delay was to ensure that Members had enough time to consider the reports and the expert opinions of the NAO and the PAC. To me, that seems entirely sensible. I thank everyone who was involved in the preparation of those reports, including the hon. Member for North Cotswolds (Sir Geoffrey Clifton-Brown).
The NAO report warned:
“There is no way forward that does not incur cost and risk, with inaction itself being a choice with serious consequences.”
I agree. As the NAO sets out:
“The costed options provide enough information for a decision on the way forward”.
The Public Accounts Committee said:
“Having scrutinised the costed proposals, we consider there is enough information to inform a debate and a vote.”
I agree with that, too—but it seems that, as ever, the Opposition think they know better.
We have been around this track before. We debated, re-debated, picked and unpicked options for more than 10 years while the Conservatives were in government. We do not need another review. We need resolve. The House needs to decide whether or not to tackle this issue.
Jerome Mayhew (Conservative, Broadland and Fakenham)
One of the key reasons why the costs are so exorbitant is the enormous contingency increases, ranging from the lowest at 32% to the highest, which goes up to 135% of the core base price. The primary reason, in addition to the fact that this is an old building, is that, collectively, we are terrible clients: we do not know what we want, we have not decided what the scope is, we change our minds the whole time and we have labyrinthine governance that includes both Houses, the Commons Commission, the Lords Commission, the client board, the programme board and its sub-board, the Commons Clerk, the Lords Clerk, the client team, Strategic Estates and the delivery authority. No one is in charge. If the Leader of the House is serious about our progressing this, he first has to get simple, accountable governance that we can all believe in.
Alan Campbell (Labour, Tynemouth)
I will come to that point in a minute, but the hon. Gentleman hits the nail on the head about the cost of contingency, which is in some of the numbers. I will tell him why they are so high: because any company that comes along here will look at how much the job will cost and then build in risk. The reason it builds in risk is that this House has never made up its mind. Anybody looking from the outside, and any company, will question whether we will ever be serious about this and whether we will continue with the plan that we have.
Let me just say this and be somewhat controversial, I suspect, to people on both sides here. It is my considered view that one of the reasons it has become so elongated and things have chopped and changed is not because politicians have not been in charge; it is because politicians have stuck their finger into, messed about with and changed almost every decision. We have had an Act. We have had review after review. It is not that businesses come in and seek to take us for a ride; it is the fact that politicians cannot make their mind up and then stick to it.
We have to be honest about the state of this building, and that is something the Opposition motion fails to acknowledge. One of the reasons that the pause and review approach is so troubling is that the building that we occupy is in managed decline. It is a decline that pause will not change; it will simply make it worse. Since 2016 and the publication of the costed proposals, there have been 36 fires, 12 asbestos incidents and 19 stonemasonry incidents. The House authorities have assessed that while current mitigations would protect human life in a major fire, they cannot prevent the loss of the building itself. Every week, £1.5 million of public money is spent on patching up decaying systems, and that figure is set to rise to £2 million a week. Only 12% of the Palace is step-free and accessible. That is entirely unacceptable for a modern legislature.
Wendy Morton (Conservative, Aldridge-Brownhills)
The right hon. Gentleman seems somewhat rattled this afternoon—certainly towards me, anyway—but putting that aside, can he not understand that those of us on the Conservative Benches are simply seeking more detailed information? I will speak later, but an example would be the information that I have failed to get in response to my written parliamentary questions.
Alan Campbell (Labour, Tynemouth)
I think “frustrated” would be a better description than “rattled”. There will be ample opportunity to get information. The right hon. Lady might even get information from this debate, but she will certainly get information over the next two weeks as we approach a decision moment.
Since my appointment as Leader of the House, I have sought to find a pragmatic, financially responsible way forward that carries as great a consensus as possible among Members across the House, and I intend to announce during the business statement tomorrow a full day of debate to allow the House to decide on 8 December. If the shadow Leader of the House, the right hon. Member for Hereford and South Herefordshire, thinks that a Tuesday is a quiet day in the House, he probably needs to get out more. That motion has been tabled today, in good time before the debate.
I want to ask the right hon. Gentleman a question. Do the Opposition intend to whip their MPs on that day? If he says no, that is funny, because until yesterday that is exactly what they intended to do. I understand that they are not whipped to vote on the motion today, but I suspect that yesterday afternoon they were whipped to vote on it. I sense that an element of realism is coming into the Opposition’s whipping. Whipping on that side of the House is a matter for the Opposition. Whipping on this side of the House is a matter for us. But this is not a debate on House matters called in Government time. This is an Opposition day debate. The Government are perfectly entitled to get their MPs here and, if necessary, vote down an Opposition motion.
Julian Smith (Conservative, Skipton and Ripon)
I have been an advocate of the “kicking the can down the road” strategy, because this proposal has not made sense financially and it is still not proven. However, as the motion says, the Opposition also accept that the situation is not sustainable. It is quite clear that all this motion is asking for is further analysis. We have heard that from the hon. Member for Boston and Skegness (Richard Tice) and from the Opposition Front Bench. There is no risk in taking a few more weeks before the Leader of the House’s motion is put in front of Parliament, so as to have as much consensus building as possible, because the challenges are quite legitimate.
Alan Campbell (Labour, Tynemouth)
I do not like disagreeing with the right hon. Gentleman, but I think on this he is just wrong. The reality is that if it goes into next year, the costs will continue to go up every week in that time. Every week costs between £1.5 million and £2 million. We have been through this process for long enough. What we need to do is make a decision.
I will put before the House exactly the plan that the House would be asked to agree or not agree on 8 December. I believe that is a responsible way of bringing forward an important matter. The shadow Leader of the House, the right hon. Member for Hereford and South Herefordshire, has asked for notice of the debate and he will be getting notice of the debate. In fact, he has already got it. I have also written to all Members with an offer to speak to any and all of them ahead of the debate to discuss the motion. If the right hon. Member for Aldridge-Brownhills (Wendy Morton) has questions, I look forward to speaking to her. In contrast, the Opposition have chosen to offer the House, at minimal notice today, a motion that offers no solutions, ignores the mounting risks and simply kicks the can further down the road.
Alan Campbell (Labour, Tynemouth)
I will not take interventions, as I am going to make some progress.
Geoffrey Clifton-Brown (Conservative, North Cotswolds)
On that point, will the Leader of the House give way?
Alan Campbell (Labour, Tynemouth)
I should give way, as I have mentioned the hon. Gentleman.
Geoffrey Clifton-Brown (Conservative, North Cotswolds)
I am grateful to the Leader of the House for giving way. I had not really intended to intervene, but I have been listening carefully to the debate, much of which I agree with: I think the costs are too high, the governance is far too complicated, and too much about the whole matter has been discussed behind closed doors, in secret.
I would like to get one concession from the Leader of the House today. I have looked at his motion very carefully. One of the key recommendations of the PAC, which I have the privilege to chair, was that this Parliament, although it cannot bind its successor, recommend to the next Parliament to have an early vote, in 2030, which would give the authorities plenty of time to see if they could get the costs down, and sort out the governance and a way forward. Would he give serious consideration to that before he puts his motion before the House?
Alan Campbell (Labour, Tynemouth)
It may not be a decision for me, but that will become self-evident when we get into the initial programme of seven years. There is initial work that needs to be done when that option is put before the House in mid-2030. One of the issues to look at will be governance and another will be financial costs. We will have an annual debate, every year. The hon. Gentleman knows that because we have talked about the role that the PAC might want to play in all this. Although I would be very surprised if I was in the job that I am doing now when we get to that time, I would find it extraordinary if, when the House had a view on the costed proposals or anything else, there would not be an opportunity to have a debate on those matters. It is not about shutting MPs out of this process; it is about getting on with it and making sure that the right people are there to drive it.
Richard Tice (Reform UK, Boston and Skegness)
On that point, will the Leader of the House give way?
Alan Campbell (Labour, Tynemouth)
Go on, then.
Richard Tice (Reform UK, Boston and Skegness)
I will take the Leader of the House up on the offer to meet him. He is correct: of course we want to ensure that the fire and safety measures are updated and appropriate for this place, but the truth is that the scope of this restoration and renewal is far broader than that in order to make the building net zero compliant. Here is the flaw. There are 50 lifts in this building, and after this programme of restoration and renewal, there will still be 50 lifts in the building, but not a single one will be in the same place.
Alan Campbell (Labour, Tynemouth)
That is a bit rich coming from the hon. Gentleman. When he was asked about accessibility at the time of the Modernisation Committee’s report on the subject, I remember him saying, “Nobody is coming to this House to complain about accessibility to the building.” Well, that is because they could not get in.
During the process that I am quickly going to outline, there is a process for all these considerations to be dealt with. It is not closing off something at this point—it is a fixed term, not a fixed plan. It will adapt over a period of time, but the key question is: are we going to get on with it? On 8 December, we will be putting before the House an initial package of phase 1 works lasting seven years, capped at a maximum of £3 billion. This is for essential groundwork, and investment in resilience and enabling works, which must happen no matter which final route we take. It caps our immediate investment and keeps long-term options open.
Let me also say—in response, I think, to an intervention taken by the right hon. Member for Hereford and South Herefordshire—that the package also takes into account best practice for major programmes. It reflects advice from the Government’s Office for Value for Money by ensuring that delivery plans are sufficiently mature before final decisions are made, to avoid unrealistic expectations about cost and schedule. The NAO has described phase 1 preparatory works while progressing the programme as “sensible”. We narrow two paths. We get the programme moving. We save on unnecessary, wasteful expenditure. The client board will provide updated costs by no later than 2029, enabling a final, informed decision on whether or not to decant by the middle of 2030.
Graham Stuart (Conservative, Beverley and Holderness)
On that point, will the Leader of the House give way?
Alan Campbell (Labour, Tynemouth)
This is the last intervention that I will take.
Graham Stuart (Conservative, Beverley and Holderness)
I understand the frustration of the Leader of the House. I recognise that getting leaner governance will be like herding cats. My right hon. Friend the Member for Hereford and South Herefordshire (Jesse Norman) challenged him on this. There is a real role for the Leader of the House to bang heads together and make sure that, whatever we decide going forward, we do not have this ludicrously complex set of intertwined governance. Does he agree and does he accept his personal role in trying—however challenging that may be—to bang heads together and get a leaner set of governance arrangements?
Alan Campbell (Labour, Tynemouth)
Yes, I do. One of the first jobs in phase 1, if we agree to go down that path, is to get the governance right within six months. I agree with whoever read out the list of all the bodies involved in governance: it is madness! It is like spaghetti, and I find it incredibly difficult to understand. We need to get a better, leaner system. It needs to be clear and people need to be accountable. But we cannot really start that process, I am sorry to say, unless we get on with phase 1—because it costs.
I understand the costs issue, but delay is not a saving. A 90-day review, supported by the shadow Leader of the House, would cost £100 million and would not guarantee progress at the end. All we get is the warm bath of endless review from the Opposition, but at what stage will they accept the stark warnings of the National Audit Office, the Public Accounts Committee, and every independent assessment the House has ever commissioned?
Let me turn briefly to an issue that the right hon. Member for Hereford and South Herefordshire was a bit sniffy about, actually: the benefit to the country. This building does not belong to us; it belongs to the nation, and we have a responsibility to restore it. This programme will bring not just costs but benefits. It will invest billions of pounds into supply chains reaching into constituencies right across the country. We will draw on the industrial expertise and craftsmanship of the whole nation. We will back up 4,000 jobs and 1,000 apprentices.
I know that the shadow Leader of the House, the right hon. Member for Hereford and South Herefordshire, cares passionately about this building and the work we do in it, but I have to say to him and to others: passion alone is not enough to put out a fire, and another review will not make the project move forward in any way. We have an opportunity to halt the cycle of delay and cut wasteful expenditure. The Opposition propose a pause without a plan, a recipe for continued decline, a guarantee of hundreds of millions of pounds wasted in delay, and an acceptance of the increased risk of catastrophic failure. We cannot accept that approach, and we cannot accept this motion. I therefore commend the Government amendment to the House.
Nusrat Ghani (Conservative, Sussex Weald)
Order. Before I call the Liberal Democrat spokesperson, let me say that this is a time-limited three-hour debate, so I hope colleagues will manage the length of their speeches.
Lee Dillon (Liberal Democrat, Newbury)
Since the beginning of this week I now sit on the House of Commons Commission, which, together with the House of Lords Commission, makes up the client board for this programme—there has been some quick reading and quick learning!
I thank the Opposition for tabling this motion. I say that with some affection, because it is not every day that a party turns up to complain about its own homework. Nobody in this House should be relaxed about spending tens of billions of pounds of public money, and the Liberal Democrats share that concern. But let us remind the House whose idea this was. A Conservative Leader of the House, Dame Andrea Leadsom, tabled the motions in 2018 that sent this House on its way out of the Palace. A Conservative Government introduced and passed the Parliamentary Buildings (Restoration and Renewal) Act 2019, and when Notre-Dame burned down that year, a Conservative Leader of the House told us all to “get on with it”. Now, a Conservative Opposition table a motion expressing “grave concern.” Grave concern about what exactly—their own signature?
Andrew Murrison (Conservative, South West Wiltshire)
The grave concern is the truly eye-watering sums that are being debated. My constituents, and I suspect those of the hon. Gentleman, will be appalled that we should be spending that sort of money on ourselves—and that is how it will be presented, rightly or wrong. Does he not share those concerns?
Lee Dillon (Liberal Democrat, Newbury)
I absolutely share those concerns, but the motion in the name of the shadow Leader of the House, the right hon. Member for Hereford and South Herefordshire (Jesse Norman), would involve the largest possible range of options being available. I would not support that; I would support the cheapest option on the table.
Andrew Murrison (Conservative, South West Wiltshire)
That has been discounted.
Lee Dillon (Liberal Democrat, Newbury)
No, the coming motion would take our choice down to two options. Concern is fair, but concern is not a plan and the motion does not offer one. The Lord Speaker, who chairs the client board, wrote last week:
“This is not a party political matter and a decision is best reached by consensus.”
I would argue that an Opposition day motion is not the way we reach such a consensus.
Let us look at the figures in the motion. The range of £11.1 billion to £39.2 billion is not one project but two options stapled together.
The National Audit Office puts the cost of full decant at £15.6 billion over 19 to 24 years and the cost of enhanced maintenance and improvement-plus, or EMI+,—at £19.5 billion to £39.2 billion over 38 to 61 years. The figure that so alarms the Opposition belongs to the option in which Members stay in the building, but the cheaper, quicker option involves us leaving. Their motion complains that staying put is too expensive, but, in the same breath, it questions the plan to leave. That is not a policy; it is the Conservative party having a tantrum.
Notre-Dame has about 5% of the floor space of this Palace and cost in the region of €700 million. If we multiply that figure by 20, we land close to the bottom of the full decant range. Buckingham Palace has lessons for us to learn on phasing and asbestos, but it is half the size of this Palace and has one sixth of the users, and its costs left out stonework restoration and fire safety. It is not a like-for-like comparison.
Joshua Reynolds (Liberal Democrat, Maidenhead)
Given the fact that the motion before us is unnecessarily confused, jams together different options and does not lay things out clearly, any confusion that our constituents may have today is actually because of the Opposition making them confused and angry about potential spending that is significantly above the range that we should, in reality, be discussing. Does my hon. Friend agree?
Lee Dillon (Liberal Democrat, Newbury)
I agree. This is the Conservatives trying to cause an argument for the sake of publicity, rather than because of the real detail.
There is no quick or cheap method waiting to be revealed, and delaying until one turns up is hope, not a plan. The cost of postponing this debate alone is more than £200 million. Some £500 million has gone on design consultancy and the delivery authority, which costs more than £1 million a week and will soon have nothing to do without a decision. That is the real waste.
Rebecca Smith (Conservative, South West Devon)
I assume that the hon. Member will get further into the detail of the length of time that this work will take. We are focusing quite significantly on the cost, but ultimately this will potentially mean decades of time in which our constituents will not be able to access this mother of all democracies—the Palace of Westminster. Is it the position of the Liberal Democrats that the public should be kept out of here for a significantly long period of time? Do they not want to minimise the distress caused to them?
Lee Dillon (Liberal Democrat, Newbury)
The interesting thing about that intervention is that the greater number of years and the higher cost relate to the Palace being in constant use. If we went for the cheaper option of decant, Members and the public would be back in the place sooner.
What the Conservatives propose is not restoration; it is dithering. Uncertainty is not free. The Lord Speaker points out that where the scope is unclear and decisions are delayed, contractors put a risk premium on their prices. The Leader of the House also noted that. Every month without a decision adds to the bill.
The 2019 Act set clear tests: good value for money, consultation with Members and staff, and a prompt return to the Palace. That legislation was passed by a Conservative Government. They said that there would be no blank cheques, and they wrote those tests. We are simply asking that some of them are met.
What is actually being proposed is more measured than the motion pretends. The first phase is capped at £3 billion—about £429 million a year over seven years, excluding inflation. Around 85% of the Palace’s construction costs are priority works, such as power, water, heating, fire safety, asbestos and stonework.
Mark Francois (Conservative, Rayleigh and Wickford)
As a former Government accommodation Whip, I absolutely accept that we have to do something about the fire risk to the Palace. The hon. Gentleman has said that we should try to proceed by consensus, and I think everyone agrees that whatever we do, we must do something about that. However, does he accept that whether it is £10 billion or £40 billion for the overall solution, at a time when people’s gas prices are about to go up and they are feeling the cost of living challenge, the problem is that we would be perceived—rightly or wrongly—as spending that money on ourselves? That is the fundamental nub of the problem.
Lee Dillon (Liberal Democrat, Newbury)
I do not accept that we are spending money on ourselves; Members are, in effect, one of the smallest groups of employees in this Palace. It is about protecting the 3,000 people who work here, and ensuring that we have a safe and welcoming environment for our constituents.
As I said, more than 3,000 parliamentary employees work here, and the motion forgets to mention them. Asbestos has been found and, in several cases, released during general maintenance, meaning that the workers affected now face lifelong health monitoring. Legionella has been found in the water supply. Fire, leaks and flooding are daily risks. Last night, we had a sewage tanker brought in to drain the toilets, and I know that the toilets downstairs were not in use this morning either. It is often those who are paid the least—the cleaners and the catering staff—who carry that risk. No other employer would ask people to carry on like this.
The building is too hard for disabled staff and visitors to use. Having been on crutches, and now a stick, over the last few months, I have come to realise how awkward it can be to get around this building. The plans would increase the step-free floor space from 12%, where it currently stands, to 60%, and up to 90% in the areas most used by Members and visitors. Most of that comes straight from essential fire safety work. Fire evacuation lifts, for example, are needed to get people out safely, and they open up step-free access as a result.
The Leader of the Opposition has called the plans a “net zero Dubai hotel”, but the returned Palace will not be net zero. The Education Centre and the visitor entrance account for just 0.8% and 2.7% of the construction costs. What this programme is really about is having a safe workplace, a building that everyone can use, and jobs and apprenticeships across the United Kingdom.
The Lord Speaker, who co-chairs the client board, has asked whether that board of around 25 members, as well as the programme board of 15 members, provides clear leadership and accountability. That is a question that I also have. Since the client board is made up of the two Commissions, and I now sit on one of them, I will not pretend that it is for somebody else to answer.
Before the letter from the Leaders of both Houses arrived in our inboxes earlier today, I was planning to push for a clear timescale for the decisions; the cost and risk information that Members need; answers about who is accountable for cost control; a commitment that Members will see the whole-life cost, including the cost of delay, before any vote; and regular reports on the £3 billion cap and on progress on access for disabled staff and visitors. I welcome the fact that the Leader of the House outlining that in his letter.
Let me conclude with a word about the Conservative party.
Graham Stuart (Conservative, Beverley and Holderness)
You’re obsessed!
Lee Dillon (Liberal Democrat, Newbury)
It is your Opposition day.
Nusrat Ghani (Conservative, Sussex Weald)
Order. It is not my Opposition day. I remind the hon. Gentleman that he is speaking through the Chair.
Lee Dillon (Liberal Democrat, Newbury)
It is the Conservatives’ Opposition day, Madam Deputy Speaker, and I think it is right that we address them, in particular.
The Conservatives had a Prime Minister who campaigned to remain in the European Union, they had a Prime Minister who legislated for net zero by 2050, and they proposed a sensible approach to restoration and renewal, which we are now debating today. They were right then, but now they just look like a populist party. They could have tabled a motion about provision for special educational needs and disabilities, which is failing families in every constituency, or they could have tabled a motion on the state of the water industry or the defence of the country. Instead, they have brought us a press release in the form of a motion about a programme that they started, and it offers no alternative.
That is why the Liberal Democrats will abstain this evening. The motion deserves neither our support nor our opposition. The issue deserves a decision, and this motion does not make one. We cannot back a motion that questions the decant by keeping the price of delay off the page, but neither will we vote against a call for proper financial control and accountability, because a programme of this size needs that. We will keep pressing for value for money, transparency and a clear timetable, and we will hold the Government to account—and I will hold myself to account, as a member of the Commission—on all three.
Nusrat Ghani (Conservative, Sussex Weald)
About 20 colleagues are trying to catch my eye, and this debate has to conclude before 6 pm. Can Members please keep their speeches short?
Nick Smith (Labour, Blaenau Gwent and Rhymney)
I rise to speak in favour of the Government’s amendment. I support a restoration and renewal programme that happens at the right pace, and that ensures good value for money. Dame Andrea Leadsom, the former Conservative Leader of the House, when introducing the R and R programme in 2018, said:
“We do need to get on and take a decision”.—[Official Report, 31 January 2018; Vol. 635, c. 887.]
I agreed with her then, and I still agree with her. It is up to us to move this forward.
We are the custodians of this brilliant place. Now is the time to invest in, and improve, our democratic home. It will take more time than we want, because it is such a vast estate with so many aspects to protect. It will cost more money than we want to spend, but the fine stone, the beautiful windows, the great works of art and, of course, this wonderful Chamber all need to be properly looked after. In the end, I believe the effort will be worth it, but we must help bring the works in at a good price. There are other benefits; our economy will receive a much-needed boost from skilled people across our country carrying out these necessary works. Many parts of our country will benefit, whether it is the slate coming from Wales or the textiles coming from the west midlands.
If we do not move forward with the restoration and renewal programme now, there will be serious consequences. We face critical risks, including fire, asbestos and falling masonry. Anybody who has been down to the basement of the Palace and seen the archaic muddle of pipes and wiring there will understand what I mean. While the Palace is a UNESCO world heritage site and the Elizabeth Tower is a global icon, most of all, the people of this country know that it is this Chamber—where we raise and work through the difficult challenges facing our world—that we must protect. That is why this place is worth investing in, and why it is priceless. It is our duty to invest in it, and when the work is done, we should return to this democratic crucible.
The works cannot be done on the cheap, and we should have strong financial controls and oversight of them. Of course, as the Leader of the House has said, doing nothing also costs a lot. We presently spend £1.5 million a week on maintenance and repair; if we delay, those costs will go up and up, again and again.
Jamie Stone (Liberal Democrat, Caithness, Sutherland and Easter Ross)
Will the hon. Member give way?
Nick Smith (Labour, Blaenau Gwent and Rhymney)
I will.
Nusrat Ghani (Conservative, Sussex Weald)
Order. Before the hon. Member makes his intervention, I note that it is customary to be in the Chamber for a while before an intervention is made. Can he confirm that he has been here for a while?
Jamie Stone (Liberal Democrat, Caithness, Sutherland and Easter Ross)
I cannot, Madam Deputy Speaker. I was late, and I apologise.
Nusrat Ghani (Conservative, Sussex Weald)
Marvellous. Continue, Nick Smith.
Nick Smith (Labour, Blaenau Gwent and Rhymney)
This work cannot be done on the hoof. There are around 1,100 rooms in this Palace, and many different buildings from across the ages. France rebuilt Notre-Dame in five years and eight months at an estimated cost of £600 million; however, as has been said, we must remember that Notre-Dame has only 5% of the floor area of the Palace of Westminster.
Sadly, I think that the approach taken by the official Opposition today has not been constructive at all. I hope that as we get nearer to the vote on costs, a degree of consensus will emerge across the House. The initial £3 billion-capped phased programme ahead of us focuses on investment in underground construction, wiring and plumbing, building temporary Chambers, and restoration of the wonderful medieval cloister court. A “make do and mend” approach is not going to get us anywhere, and a 90-day red team review—a rabbit out of a hat—is not a serious proposal. Let us get on with it.
Nusrat Ghani (Conservative, Sussex Weald)
I call the Father of the House.
Edward Leigh (Conservative, Gainsborough)
I first got involved in this issue over 10 years ago. Our colleague Jacob Rees-Mogg, who has been mentioned, served on the original Committee that 10 years ago recommended a full decant to Richmond House. It did not fill us with great enthusiasm that that Committee got its measurements wrong—the IKEA-style chamber could not fit into that part of Richmond House, and of course there would have been enormous expense. I have been working on this issue all this time, and it was apparent to me 10 years ago that we were constantly proposing gold-plating and decanting instead of getting on with the work. The delivery authority—all this period, and certainly from 2019—has been spending vast amounts of taxpayers’ money endlessly developing plans and not repairing the building. It has proposed endless gold-plating works, and it has devised completely unnecessary new ideas, such as a new underground visitors’ entrance.
I agree that it is very hard to make things happen in politics, but if you are relentless, you can stop things from happening. I know that I have been a deep disappointment to the right hon. Member for Alyn and Deeside (Sir Mark Tami).
Mark Tami (Labour, Alyn and Deeside)
True. [Laughter.]
Edward Leigh (Conservative, Gainsborough)
I served with him on these boards for many years, and I did my best to constantly argue, “Please just get on with it.” Eventually, I could not take it any more, and I had to resign from them because of the endless delays.
I agree that this is a world heritage building that we love, but at the end of the day it is just a building. All this work has accumulated in a Byzantine structure of layered bureaucracy and committees, officials and consultants. Fractured responsibility and an inevitable lack of accountability is leading year after year to a ballooning bill, with potentially billions wasted on unnecessary works. That is fertile ground for contractors seeking to take advantage to charge what they like for unnecessary works. I have constantly questioned that on these boards, saying, “Why are we not just repairing this building?” We are proposing to spend £40 billion, but we do not yet know the agreed budget. It has not been finalised, and there is no settled scope and no clear accountability to Ministers and the House.
Costs are merely estimates. We have £11 billion to £39 billion—for a building! There is a huge amount of uncertainty on which to make decisions. This building was built superbly by the Victorians. Of course it needs maintenance, like all historic buildings, but it is fundamentally sound. The electrical services are complex and in places they are in a mess. We have all been down into the cellar again and again to look at them, but we do not need 15 years of full decant to deal with them.
In my view, the problem started when we created the September sitting. Previous Conservative Leaders of the House have been mentioned again and again, and there has been talk of delays, but I hope that people accept that I have at least tried to be consistent on this point about the September sitting. I have made it again and again and been ignored. The problem started when we created it. Years ago, this building was effectively closed from 20 July when we went into recess until 12 October. Everywhere there were workmen working, but we have just bled the building dry. We have even had the public coming in so that they can have lunch in the Members’ Dining Room—very nice, too—but the building is more important. The September sitting is where many of these maintenance problems started.
I know that Governments are wary of changing it, because the September sitting is The Daily Mail sitting. The paper might say, “Oh, these MPs are lazy,” and all that, but there is a perfect excuse: this building has to be worked on—it is an old building—for three months or even four months every year without interruption.
Rebecca Smith (Conservative, South West Devon)
I thank my right hon. Friend for making that point, which I was hoping to make myself. Does he agree that 2010, when the September sitting was fully introduced, to 2026 is 16 years, and that six weeks times 16 years is 1.8 years of time that could have been spent working on this place? That is a huge missed opportunity. The renovation work that he speaks of so eloquently could have been happening, and we would now be looking to restore a different Parliament.
Edward Leigh (Conservative, Gainsborough)
That is a very good point. I have argued again and again—and been ignored—that we should repeal the 2019 Act. That is the real problem that has been delaying everything. We cannot do proper works because we are bound by the delivery authority and by the Act. We should abolish the delivery authority. We should get on with it.
Some may say, “These people are just selfish. They never want to decant.” There may come a time when we have to decant for a brief period—maybe a month, a year or two years—but we should get on with the work, such as on asbestos in the Chamber. The best way to deal with asbestos, by the way, is to leave it alone, but I put that to one side. We are not ideologues on this. We are prepared to decant for six months, a year or two years if those who advise us say that it is necessary, but we cannot decide all these things in a vacuum. We have to start the work and prepare it.
A full decant would be extremely costly, and, according to some estimates, would involve as much as 19 to 24 years away from the Palace. Some people think there is a risk that we would never come back, although actually I do not think that is true: I think that we would come back, and would then be amazed that the thing was exactly the same, with the same pictures in the same places, after 24 years. A whole generation of MPs would be deprived of participating in this historic building.
I am not selfish about this. I am quite happy for us to decant, because by the time we decant I shall be in my grave, so I do not care for myself. However, I do care for this building and for future generations. Most important, this is a symbol of the nation. When people across the world think of the United Kingdom, what is the photograph that flashes into their minds? It is the Palace of Westminster. This is not just a building. It is a working building. It is not just a monument. It is not just a museum, although some people want to create it as one. This is about the “mother of parliaments”. It has to be occupied.
By the way, I have worked with Prime Ministers and Leaders of the House all along the line on this issue, and they all pay lip service to moving out, but when it comes to it, no Prime Minister ever allows the decant to happen. You do not become Prime Minister after all those years and then end up in Church House or Richmond House. Let us be completely honest about this: they have been kicking it into the long grass because they do not want to decant, and they have got a point, because this building is the symbol of the nation.
Julian Lewis (Conservative, New Forest East)
I am slightly surprised that the Father of the House is so optimistic that he thinks that after years away from this building, we would come back—I really doubt that—but given that the proposal is to reduce the four available options to two, would it not be sensible to remove the full decant option and choose between two of the other three options that offer a variety of different ways in which we could stay in this House?
Edward Leigh (Conservative, Gainsborough)
I do not know about that. It may be a fair point, and it does reveal part of the problem. When it comes to this building there are so many different opinions, so I have some sympathy for the Leader of the House, which is why I have consistently argued—I hope—that we just have to get on with the work.
As we all know, the real risk is fire. I have argued again and again that we need fire doors in corridors that are 100 yards long, but apparently we cannot put them in because English Heritage will not let us do it. I have argued for sprinklers for years, and they were installed in the basement, but then the “blob”—the authorities—said, “You cannot turn them on because the firemen might get Legionnaires’ disease.” But the building might burn down! I have asked for sprinklers in every room, and the establishment has said, “You cannot have sprinklers, because English Heritage said that the pictures might be damaged.” But if there is a fire in the building, the place will burn down. Notre-Dame has, of course, been mentioned, and the cause of that fire was the ongoing works. That is the real danger: workers with blowtorches and so forth. The recent record for this sort of work, as we know, has been disastrous. The atrium roof in Portcullis House was replaced after only a quarter of a century, and a massively expensive door has been provided for the House of Lords. It cost £10 million, and it does not work.
I sincerely believe that the last thing we should do is to vote through either of these options, which would mean more years of delay, more planning for gold-plating, and more costing that cannot be evaluated. We should all read the excellent letter from the Lord Speaker. It is all there. It says:
“The Costed Proposals report recommends authorising up to £3 billion of preparatory expenditure over the next seven years”.
That alone is extortionate, in my view, and illustrative of the fact that this will be a very long-winded, expensive, ultimately dissatisfying and potentially disastrous process if pursued in the wrong way. We have been addressing these issues in the most expensive way at a time when the public purse is strained. What would the public make of these figures when there is so much pressure on our hospitals and schools, for instance, and when we are spending so much money on ourselves? They pay for all this. They would be astonished, and they deserve better.
Let us pause on what we are talking about. A full decant of the building would cost £11.5 billion, excluding inflation, or £15.6 billion with inflation, and it would take up to 26 years. EMI+, which we have not heard a lot about, could cost up to £39 billion and take 61 years. This is not sensible. I agree with the Lord Speaker that we need
“a clear and agreed specification of essential works”.
There should be no gold-plating, but we must make the building safe and restore it.
Joshua Reynolds (Liberal Democrat, Maidenhead)
The right hon. Gentleman has mentioned gold-plating a few times, but he has also said that this building is the jewel in the crown for the United Kingdom. He mentioned the underground visitors’ centre, which I want to ask him about. I do not know if he has been to the current visitors’ entrance recently, but I have, and I do not think it is befitting of a grade I listed building. What would he do differently in this situation? What is he actually proposing?
Edward Leigh (Conservative, Gainsborough)
I would repair the building! I would make it safe, which is what we should have done 10 years ago, and make sure that it does not burn down. That is what I would do. We do not need a new visitors’ entrance, a Nelson Mandela room or anything else. The building works. Let us just get on with it.
I have served on the R&R boards, and it is staggering. There are 25 members on the client board, and 15 members on the programme board. The delivery authority has been working on this since 2019, and has been endlessly developing plans but not doing anything. My final words: just get on with it.
Peter Dowd (Labour, Bootle)
Madam Deputy Speaker,
“Without action, at best the Palace will be in a process of managed decline. At worst, a catastrophic event could occur that endangers lives and interrupts the functioning of democracy in the UK…A failure to act would have serious consequences for taxpayers and future generations.”
These are not my words, but those of the Public Accounts Committee—which is chaired by the hon. Member for North Cotswolds (Sir Geoffrey Clifton-Brown), who is not here today—in its report, “Restoration and Renewal of Parliament: Costing and governance”, and the devil is in the detail. That is a fair assessment by a cross-party group of 16 MPs.
The Committee set out a number of conclusions and recommendations. There were eight in total, including engagement with parliamentarians, a timetable of work from the client team, and the question of a “competitive dialogue” procurement approach in relation to gaining clarity on the scope and the cost band schedule. In addition, the Committee set out the remaining cost estimates for phase 1 and suggested a detailed delivery schedule.
The Committee also recommended the production of an integrated plan across a number of themes and a temporary accommodation proposal, as well as setting out the risks associated with divided responsibilities. Then there was the recommendation about the simplification of the phase 1 governance process, which will be reviewed ahead of the start of phase 2. That covers a number of the issues that Members have raised today. The final two recommendations relate to a potential restoration and renewal Select Committee, based on the Canadian model—I make no comment about that, but the Public Accounts Committee put that in its recommendations—and to an annual update on the programme’s progress, with an independent annual examination of the programme.
Those recommendations are set out in the context of a full decant of both Houses, which would cost £11.1 billion to £15.6 billion over the best part of two decades—I suspect that some of our younger colleagues will still be Members of Parliament at that stage—and a continued presence for up to 45 years, which would cost £22 billion. Then there is the enhanced maintenance and improvement proposal, which would cost £56.3 billion and take between 52 and 84 years. Finally, EMI+ would cost up to £39 billion—and so it goes on. However, the latter options are less developed and more uncertain.
At this stage, I would say that I have always been able, notwithstanding the complexity of the issues and the cost programme, to get information from the appropriate teams, including regular information sessions in Portcullis House about the programme. I have managed to get lots of information; if other Members have not got the information, it is not because it is not available. It is there, and if Members choose not to look for it or to do a bit of research, that is a matter for them.
Phil Brickell (Labour, Bolton West)
My hon. Friend is making a very good point. Does he recognise that the independent advice and assurance panel itself recommended the scale of works proposed by the restoration and renewal programme, that the R and R client board’s assessment at the end of last year checked and benchmarked the proposals against comparable projects, including Manchester town hall, and that delivery costs per square metre are similar to those for the Canadian Parliament when judged by volume?
Peter Dowd (Labour, Bootle)
My hon. Friend makes a really important point. There is a lot of ultracrepidarianism going on here. People who think that they are, or may even be, experts in one field seem to think they can make judgments in an expert fashion about things that frankly they do not know very much about. It is also called epistemic trespass. I suggest that Members go and have a look at what that means, if they are not an expert on it.
In July 2022, both Houses—the Commons on 12 July and the Lords on 13 July—agreed a mandate, unamended and without a vote, that in effect the vision for the restoration and renewal programme would be
“preserving the Palace of Westminster for future generations and ensuring the safety of all those who work in and visit the Palace, now and in the future”.
It is now the job of this House to put that intention into practice. I fully appreciate that Members across the House have differing views about the timetable and the costs. Having decided on phase 1, for example, is it not time to just move on? I think the time has passed for continuing the debate about whether we want to do it, because it is time to move on. We really need to act.
We need to stick to a timetable for making decisions without further prevarication, because that is all I have heard today. Have we not prevaricated enough over this? At what point do we stop asking for more information, more facts, more projections, more reassessments, more surveys and more re-evaluations? The longer we delay, for whatever reason, the more money we will be asking the taxpayer for.
Jamie Stone (Liberal Democrat, Caithness, Sutherland and Easter Ross)
Madam Deputy Speaker, I look in your direction with trepidation, but I apologise abjectly for my tardiness. I may be about to ruin my career in this place, but if Members do not know, I served on the small committee that oversaw the building of the Scottish Parliament. [Hon. Members: “Ooh!”] Members may well say “Ooh!” What I know from the experience—I speak bearing the scars—is that every time there was a delay, for whatever reason, the price went up.
To that, I would add two things. First, the building was completed in 2004, and today people say, “It won the Stirling prize. What was the fuss all about?” Secondly, there is a cautionary tale here for my friends sitting to my right: the Conservatives, led by my old friend the late David McLetchie, refused to have anything to do with the building of the Parliament, which meant that they were not involved in some crucial decisions that affected the way the offices were laid out. The hon. Member for Berwickshire, Roxburgh and Selkirk (John Lamont) will remember that. I would argue, and I think the Conservatives would now argue, that it was a mistake not to get fully involved and work on a consensual and cross-party basis.
Nusrat Ghani (Conservative, Sussex Weald)
I am not sure that that was an actual intervention.
Peter Dowd (Labour, Bootle)
Kicking the can down the road, as it has been referred to today, is not going to sort out the problem. We are facing this problem now—not tomorrow, next week or the week after, but now. It is the problem set out at the very beginning of my speech, and it is the undeniable concern that many people have about the safety of this building.
In just eight years’ time, it will be the 200th anniversary of the fire that consumed this Palace in 1832. I acknowledge that in these debates we do not want to present selective and out-of-context quotes from various associated documents, for example from members of the restoration and renewal client board, as a blunt instrument. Having said that, when those documents are there, we do have to look at them and put them into context. We do not have to take them at face value, but we do have to acknowledge that they are not manufactured. The people advising us are not just sitting there making things up as they go along.
In paragraph 114 of “Delivering restoration and renewal of the Palace of Westminster: the costed proposals”, the board states:
“The independent health, safety and fire panel concluded that all delivery options could be delivered safely, including both EMI variants.”
Those are the one that will go on till the cows come home. But the panel did note that
“concurrent construction sites, continued occupation of the Palace of Westminster and longer programme duration for the EMI variants increased the risks arising in a number of areas”
and therefore increased the costs that people are talking about. I repeat that I do not want to take those observations out of context, but it is important to note that there are increased risk factors in delays to implementing the longer term plans that phase 1 wishes to put in train.
What about the concerns expressed by staff about the conditions they work in, to which my right hon. Friend the Member for Hayes and Harlington (John McDonnell) referred? Only today, we received a letter—hon. Members may have read it—from representative bodies expressing their concern about the further delays that the Opposition motion may produce. The report sets out the cost of delay. We have heard various figures: £250 million to £350 million a year in inflationary construction costs across the Parliament. That is a huge amount. If we accept the figure cited by the shadow Leader of the House, then, as the Leader of the House says, that is another £100 million to put it off for three months. Are they being serious?
We all acknowledge the importance of this world heritage site. We have to move on. I have heard comparisons with Notre-Dame, but I think that is a spurious argument. On the Hansard Society podcast, Ruth Fox and Mark D’Arcy interviewed the shadow Leader of the House—I am sorry he is not here to hear this point—and said, in effect, that it was a spurious comparison. As Members have said, this area is 14 times the size of Notre-Dame. Actually, the figures for fixing and refurbishing the building are not far off. We should not prevaricate much longer. The taxpayer is used in all sorts of forums to justify this or that expenditure on the grounds of “the interest of the taxpayer”. I do not want to rehearse those examples again; we just have to try to move the debate on.
I will finish shortly. The shadow Leader of the House—it is a shame that he is not here for this—is a Burkean scholar, so I hope he will appreciate my quoting Edmund Burke:
“It is a general error to suppose the loudest complainers for the public to be the most anxious for its welfare.”
The right hon. Gentleman, when he reads that, will forgive me, but that is what I am seeing today. I do not trust the loudest voices of the complainers, and neither did Edmund Burke. I am not suggesting that anyone is telling lies today, but I will quote the French philosopher Alexis de Tocqueville:
“It is easier for the world to accept a simple lie than a complex truth.”
This is the complex truth, and we really do have to move on. A rapid review, as suggested by the Leader of the House, is not going to solve the problem. I have heard what the Front Benchers have had to say. It is time to push on and stop dodging the issue once and for all.
Nusrat Ghani (Conservative, Sussex Weald)
I call the Chair of the Finance Committee.
Steve Barclay (Conservative, North East Cambridgeshire)
The restoration and renewal programme is best characterised as one clouded in denial. We can see that from the costs that have already been cited in this debate. Understandably, the hon. Member for Boston and Skegness (Richard Tice) quoted from the National Audit Office report. Figure 1, on page 20, sets out the cost of decant: £11.1 billion to £15.6 billion. Those NAO costs came from the fully costed proposals from the delivery authority, but Members are kidding themselves if they think that they are the true costs.
The intervention from the hon. Member for Bury St Edmunds and Stowmarket (Dr Prinsley) was a good illustration of that point. He said that we need to get on with restoration and renewal because of the work in his office on Parliament Street. That is outside the scope; it is actually covered by a different programme. It is £5.3 billion that is being spent and kept off the books. It is off the restoration and renewal books, but £3 billion of it is presented as essential to enable decant to happen. It is presented as integral to the R and R programme, but it is kept off the books.
Of that £5.3 billion, a further £1.7 billion is actually work on the Palace: bridging work over the next 10 to 15 years, much of which will be ripped out because of the delay. This is work that we are going to commit to but then remove, none of which is on the restoration and renewal books.
Phil Brickell (Labour, Bolton West)
The right hon. Member referred to the National Audit Office, which said in its update earlier this year that carrying out phase 1 preparatory works while progressing the programme is “a sensible approach”. Does the right hon. Member agree with the NAO on that point?
Steve Barclay (Conservative, North East Cambridgeshire)
The hon. Member is talking about the £3 billion that the NAO has said is for phase 1. We have taken seven years to go from one option in the original legislation to four options. Now, those in the House today who are saying that we must get on with it are actually saying, “Let’s go, over the next seven years, from four options to two.” That is the proposal.
Interestingly, most of the £3 billion that the hon. Member is talking about is not work on restoration and renewal. It is things like a temporary jetty, the QEII centre, temporary accommodation for the House of Lords and a temporary Chamber of the House of Commons. Most of that is not work on things like asbestos or work on the House, but facilitation for the future restoration. It is not dealing with the immediate fire risk that many Members have cited. That £3 billion is just preparatory work for after 2042, when the full decant actually happens.
Let me go back to the figures, because it is not just £5.3 billion that is being kept off the books. We start with £15.6 billion in the NAO report. We have £5.3 billion of work on our estate—work that our constituents will say is for MPs’ offices. We have £5.3 billion off the books, but we know that because of delays that have arisen since February, the delivery authority now says that decant is going to take three years longer, from 2039 to 2042. The Lord Speaker says that that will cost an additional £800 million. That is not in the figures given in figure 1. There is also a further £612 million, which relates to work that the delivery authority has already spent. That is not in the figures. There is other work, too, such as the £100 million or so that is to be spent on streetscape to pedestrianise Parliament Square. That is not in these figures either.
My point is that the figures are huge: we are talking about north of £22 billion. To put that in context, the Government’s defence investment plan is only £15 billion—half of which, incidentally, was unfunded, and when I challenged the Defence Secretary on the £3 billion of capital reprioritisation, he did not have a clue where it was coming from. The Treasury Committee, which has a majority of Labour MPs, has said that it is a “moral imperative” to address the freeze on student loans. That will cost about £255 million to £355 million over this Parliament.
For R and R, we are talking about north of £22 billion, which does not even include inconvenient things like inflation. The figures were based on inflation as of December last year, and we already know that inflation is now higher. That is before we get on to highly predictable cost overruns. It is great to hear the Scottish Parliament mentioned as an example: that was a programme that massively overran. The Elizabeth Tower started at below £30 million and ended up at just under £80 million. The Lords gate, which has also been mentioned, started at £3 million, ended up at £9 million and then did not properly work. We know that there is a high likelihood of cost overruns, and yet these sums are absolutely huge in the context of wider Government pressure.
The second issue is that we are ignoring advice from the people who actually know what they are talking about on these issues. Let me give an example: Lord Morse, the former Comptroller and Auditor General, was a figure respected across the House. He said that due to the constraints of the site, capacity-wise there is a limit on what can be done in any one year, using the phrase, “There is only so much you can force through the tube.”
I have not heard anyone mention the run rate. We are going from a run rate of £200 million to a run rate of £600 million by 2030—a threefold increase. Let us look at whether we are managing our existing flow effectively. Has anyone walked over to College Green car park? We took it back from Westminster council, but it is now mired in legal dispute, as my right hon. Friend the Member for South West Wiltshire (Dr Murrison) knows, because it has been allowed to go to rack and ruin. Has anyone looked at Norman Shaw North and the cost overruns compared with what we are told just last September? It has gone up multiple times. The consultancy managing the costs on that programme, incidentally, was incentivised on costs, getting more money the higher the overall programme costs—hardly driving the right behaviours. So there are issues over capacity too.
The £3 billion the hon. Member for Bolton West (Phil Brickell) mentioned is not to make a final decision; it is simply to narrow down to two options and do further enabling works.
Gareth Snell (Labour/Co-operative, Stoke-on-Trent Central)
The right hon. Gentleman has clearly studied the figures, and I know that he has a great reverence for the building that we are in. Given that he has looked at the figures and has quite a good understanding, what is the top figure he would put on spending to do the work? What I am hearing from the Opposition is all the things that are wrong, but no proposals for what could go right, other than more time.
Steve Barclay (Conservative, North East Cambridgeshire)
That is an absolutely fair challenge. To be fair, I grappled with it for a while, because it is not enough just to say what we are against; we have to come forward with solutions. I will close with exactly that point, because it is a fair challenge and people need to get off the fence. I have a very clear answer.
However, I want to say first that I think people are having the wool pulled over their eyes on the total cost, and I think Members will have other priorities in their constituencies where that money could be spent. Secondly, there are capacity issues. People need only to look at some of the existing programmes to see that. For example, the streetscape project will require changing the New Palace Yard programme, which was finished just this year. There are interplays between these programmes that we also need to consider.
I have huge respect for the Leader of the House. I do not know what the dispute is between the Front Benches, but he is someone I hold in the highest regard. However, I would just say to Labour MPs that although those on their Front Bench are saying that this is just a parliamentary matter and that it is nothing to do with the Government, we are in fact talking about taxes raised by a Labour Government, to a Labour Treasury, to fund something in a House, the majority which is made up of Labour MPs. It will be quite hard for the Minister on the morning media round to say that this is nothing to do with a Labour Government.
The Government may say that emotions come in. I spoke in the Sir David Amess debate, pointing out that we have had the full cost since February and asking where the debate was. If anyone thinks I was coming to it late, I also spoke in the same debate the year before. The Leader of the House knows that I wrote a detailed five-page letter to the previous Leader of the House, to which I got a cursory couple of paragraphs in response; I sent him that in his first week in office. That letter flagged things like the complete shambles of the governance, which is highlighted in the NAO report. These are not new issues. We have known about the governance issue. Turning back to the figure of £3 billion, people are being asked to sign that off before fixing the known governance issue.
The point I have repeatedly tried to make to colleagues is that more than half of this House is new, and yet, two and a half years in, we have still not tested its opinion. It has taken an Opposition day to float these issues, which some of us have been trying to flag as a national scandal that is going to fall before us. The Government will be responsible for this, because, ultimately, the Government have control. The Leader of the House was a Chief Whip. He knows that when there is a free vote, colleagues will often turn to those on their Front Bench and ask for a steer. I do not think it is credible for the Prime Minister to say that he does not have a view on the spending of £20-odd billion.
I will close by addressing exactly what I feel we should do. I think we should decant for a very fixed period of four years: within one Parliament, addressing the concerns of the Father of the House—equivalent to a world war in terms of time. We should have very clear accountability and reform the governance process. More than half of this House is new; we should agree as a House what the budget is. We should do as much as we can on the key risks—fire, flood and asbestos—within that time. We can do a lot of work in four years. Covid showed that when there is a will, people can work differently and work can be done quickly.
We also need to be clear about the trade-offs. There will be a difference of views. If we go from having 12% to 60% stair-free access, disability rights campaigners may say that this is money well spent, whereas others may have concerns. Reducing the energy bill by 40% may be what some people want to do, while some may feel that there are other things that can be done instead.
I will put this in context with a really small but simple example. Some of these figures are so huge that it is quite hard to get one’s head around. The Lords are in the process of repairing their cast-iron roof. The contractors gave evidence to my Committee to say that they could save £1 million if the Lords just finished at a set time—10.30 in the evening. If debate was still going on, there could obviously be a bit of flexibility and continuation the following morning.
We wrote to the Lord Speaker asking whether he would consider that. He was very open to the idea but said that it was not his decision but the Government’s. The Committee wrote to the Chief Secretary, who said that it was not her decision but the Lords’. We cannot even manage the trade-offs on £1 million of unnecessary spend, yet we are talking about a governance process retaining two options, drifting on for another seven years and kicking the can down the road while claiming that we are not binding the next Parliament.
I close with this point. The Public Accounts Committee itself has said that if we sign up to the £3 billion, we are locking in the decision. The exact wording was that
“it will be extremely difficult and costly not to proceed with the entire project”.
I welcome a debate, and I agree that there is a cost to delay. In fact, the cost of delay each year is equivalent to the student loans freeze—I think it is £320 million to £400-odd million, so it is similar. There is a real cost to this. The current approach is flawed, and I have signalled that repeatedly. It is a disgrace that we have not had a debate over the last two years to test the will of this new House. We need to do so quickly. I hope Members will engage with this issue.
Marie Tidball (Labour, Penistone and Stocksbridge)
I declare an interest as co-chair of the disability parliamentary Labour party group and chair of the cross-party Members’ accessibility group. I rise to speak against the Opposition motion, and to support the points in the Government’s motion that Parliament is an important heritage asset and a large employer and that delay in making the necessary changes will lead to soaring costs for the British public.
I make this case in support of the Government on the basis of 20 years working in disability law and policy, and over two decades driving access audits, physical adaptations and infrastructure improvements to public buildings from university institutions to civic town halls. Consequently, I firmly disagree with the Opposition that the scale of changes to Parliament as part of restoration and renewal are particularly difficult to justify. Indeed, I think the reverse. It is a great travesty that the Conservatives spent 14 years failing to implement the Equality Act 2010 in the fabric of the building that makes the laws of our country, thus driving up the cost of restoration and renewal through their dither and delay.
Making this case is especially important as we are in the middle of Disability History Month, the theme of which is “Disability, Politics and Democracy”. The accessibility of our democratic institution increases the inclusion in our politics of disabled people. When I was growing up in my constituency and deciding what I wanted to do for my degree, I understood then, as I do now, that law is power. Just as we need our courts to include representation of a wide range of protected characteristics, so too do we need to ensure that this House has the widest possible representation as the place of our nations’ legislators.
I am proud to be the first ever Member of Parliament with a congenital limb difference. Disabled people make up 20% of the voting-age population in the UK, yet at the last count only eight of the 650 of us elected to this Chamber have a disability. That is just not good enough. “Nothing about us without us” is a central tenet of the disability rights movement. This Chamber passed the Equality Act 2010, which requires public sector providers and organisations to make reasonable adjustments to their buildings, processes and services to enable disabled people to be included. It is urgent to make those changes for the representation of our democracy.
Centenary Action’s 2025 report cites the
“lack of reasonable adjustments by political institutions and…parties”
as a “major barrier” to disabled women standing for election. Indeed, article 29 of the UN convention on the rights of persons with disabilities, which the UK ratified in 2009, requires state parties
“To ensure that persons with disabilities can effectively and fully participate in political and public life on an equal basis with others…including the right and opportunity…to…be elected”
and the active promotion of an environment in which persons with disabilities can effectively and fully participate. Yet when I was elected to Parliament in 2024, there was no disabled toilet near the Chamber, there were no accessible door handles in Portcullis House—the shadow Leader of the House, the right hon. Member for Hereford and South Herefordshire (Jesse Norman), referred to that—and there was no specific means of reserving a seat on these green Benches for any of us who have mobility impairments without using a prayer or Select Committee card.
Pam Cox (Labour, Colchester)
My hon. Friend is making a powerful speech. Would she describe the measures she is outlining as gold-plating?
Marie Tidball (Labour, Penistone and Stocksbridge)
No, I would describe them as a gateway to an inclusive democracy.
This building, in which laws are made and where we ensure power is fully exercised in a way that reflects the vibrance and diversity of our proud British democracy, should be accessible and inclusive to our citizens. This Parliament is a House where all British people should feel at home: it belongs to them, too.
Thanks to the state education I had in Penistone, which helped me catch up on three years of surgeries that I needed, I was able to go on to study at the University of Oxford, where I did a law degree to understand how disabled people could have a greater role in making and changing the law. It is the honour of my life to sit on these green Benches and speak in this Chamber as the voice for the place where I grew up.
Marie Goldman (Liberal Democrat, Chelmsford)
The hon. Member is making a really passionate speech about something incredibly important: the accessibility of this building, along with attracting people from all walks of life—with all disabilities and none—to take part in democracy. Would she say something about the importance of getting people with disabilities to work here? This is also a workplace; it is not just about parliamentarians.
Marie Tidball (Labour, Penistone and Stocksbridge)
The hon. Lady will be pleased to hear that I am about to come to that.
When I was at Oxford, I spent nearly a decade working to make the places and spaces of that other great British institution and globally renowned university more inclusive. That means that I am well versed in what inclusive design looks like in beautiful heritage assets. If that is possible in one of the world’s global universities, it is possible to do such work empathetically and inclusively in the mother of all Parliaments. That matters: it ensures that disabled people up and down the country know that they can access the space that holds the seat at the country’s decision-making table.
There are 2 million visitors to this place every year; it is likely that at least 20% of those people will be disabled. People contributing evidence to Select Committees, all-party parliamentary groups and Bill Committees need access to this place, too. While they are here, they should be treated with the dignity and respect they deserve.
It is not only that; Parliament provides jobs for thousands of people. In the last two weeks, this Chamber has seen statements on the biggest overhaul of how we increase the employment of disabled people in nearly a generation. We must therefore ensure that the restoration and renewal of this building plays its own part in increasing the representation of disabled people in this workplace and in closing the disability employment gap. Our parliamentary procedures, research and constituency offices all serve our constituents better when it is easier to employ disabled staff members and when this workplace is more accessible to them—and that is not to mention the need to make sure that they are all protected from accident and injury in this workplace.
Jayne Kirkham (Labour/Co-operative, Truro and Falmouth)
Does my hon. Friend not find it incredible that 88% of this building is not wheelchair-accessible? In the case of a fire, what would happen to people who were here in wheelchairs? Again, that is not gold-plating.
Marie Tidball (Labour, Penistone and Stocksbridge)
I agree. That is the result of 14 years of Conservative dither and delay. I task colleagues on the Conservative Benches with spending a day going around this Parliament sat in a wheelchair so that they can really understand the barriers that many of us face.
John Slinger (Labour, Rugby)
Specifically on that point, I was at an event in the Churchill Room and there was a young man in a wheelchair. I decided to accompany him out of the building and it was quite an assault course to get out. I wholeheartedly agree with my hon. Friend. She is making a powerful and important speech. We need to put in investment in order to enable disabled people. They are disabled by institutions such as this House, unfortunately, and those elsewhere in the country. We need to end that and to enable them.
Marie Tidball (Labour, Penistone and Stocksbridge)
I completely agree. My experience of forging adaptations to heritage assets in other public institutions has taught me that making accessibility changes in spaces such as this one is not the Gordian knot that those on the Conservative Benches seem to fear. Perhaps they do not know that because, when in government, they avoided any action to try to unravel that knot.
Over the last two years since being elected, I have set up the first disability parliamentary Labour party grouping, along with other colleagues on the Labour Benches. That has enabled us to feed in our concerns about the accessibility of this Palace to the Government. Thanks to the hard work of the Leader of the House and the Secretary of State for Education in her previous role, a number of disabled MPs were able to contribute to the Modernisation Committee. Further to that, I have been pleased to work with House officials to establish Parliament’s first ever Members’ Accessibility Group, so that we can work cross-party to identify the changes that we need to make in this place to ensure that it is more accessible.
So far, that has led to changes such as the first accessible toilet near the Chamber, accessible door handles across the estate—though that is still a work in progress—and reasonable adjustment cards to reserve spaces on these green Benches. My thanks go to Mr Speaker and the Serjeant at Arms in particular for their support in making that happen. It is the first centralised system for Members to communicate about reasonable adjustments in the House’s history.
As the mother of all Parliaments, it is paramount that this space is accessible and inclusive so that it attracts and enables a greater group of disabled people to be represented in the Chamber, because democracy is an order of equality and non-discrimination. It is an enormous irony that this place, where laws are made, is not sufficiently accessible to millions of people to whom those laws apply.
The inclusiveness of the law and the power that it has over people’s lives is further legitimised when more disabled people have a voice, whether it is in the recent reforms to employment, the forthcoming reforms to SEND legislation or anything from the access to inclusive maternity care for disabled women to inclusive action on climate change. Embedding inclusion into this House has a filter-down effect on the inclusiveness of the laws of this land and sets the very highest bar of leadership for organisations up and down this country, including public services, which must make their workplaces more accessible.
You can only be what you can see, so we must remove physical barriers to disabled participation in this place to ensure that every disabled person who wants to make a change and be the difference can do that. I want them to hear this from us today: they deserve to be in the room and, more than that, they deserve to sit at those decision-making tables wherever they find them. Their ideas matter, their questions matter and their solutions matter. We must always put down the ladders and the ramps to enable other disabled people to rise with us into this House. For too long, our presence has not adorned the places and spaces of public life; our mark has gone unrecorded. Let us change that together today by making this place more accessible through restoration and renewal.
Caroline Nokes (Conservative, Romsey and Southampton North)
Order. I will impose a five-minute time limit after the next speaker.
Alberto Costa (Conservative, South Leicestershire)
I want to put on record my thanks to all the House officials who, over the last 10 years, have had the deeply unenviable task of trying to come up with recommendations, solutions, ideas and briefings for MPs of this Parliament and previous ones. It has not been easy for them. I agree with the Leader of the House that far too many confusing signals have been sent to House staff about what this House and the other place want. I have always argued, since I first became the MP for South Leicestershire over 10 years ago, that this building is large enough to zone off, repair and get on with it, as the Father of the House, my right hon. Friend the Member for Gainsborough (Sir Edward Leigh), has rightly reminded colleagues.
We sit in a Chamber that many, even some MPs, think is a Victorian Chamber, but of course it is a 1951 edifice. In May 1941, the Luftwaffe struck a direct hit on what was the Victorian Chamber, blowing it to smithereens. We have passed the portrait of Winston Churchill on the back stairs at the north end hundreds of times, in which he is standing in the ruins of the Victorian Chamber. Within the space of weeks, the House of Commons was relocated to the House of Lords, and the House of Lords was relocated to the Robing Room. Notwithstanding all the Victorian pipework, the asbestos and all the other infrastructure and plant that continues to work to this day, they seemingly managed to do it. People often say, “Oh, but the health and safety laws were different back then.” Yes, they were, but not so different that people were unable to work around the building and construction work.
What other buildings have commonalities with this Chamber? The Chair of the Administration Committee, the hon. Member for Blaenau Gwent and Rhymney (Nick Smith), rightly referred to Notre-Dame, but I encourage him, and indeed the whole Committee, to visit the University of Glasgow. That is another Gothic revival edifice, and it is about a quarter of the size of this building. Incidentally, the architect of the University of Glasgow was the grandfather of the architect of this Chamber that we are seated in today. We visited the University of Glasgow to learn how it was done. Over the last three decades, the main building was renovated without having to decant the main headquarters. It can be done.
I would go further. Most Members are probably utterly unaware that a few metres behind the Government Benches, a five-storey building was built in the early 1970s. The House was not decanted, the work did not create subsidence problems for Westminster Hall and we now have a car park that was built with minimal fuss in four years. That was only in the 1970s. When I first visited this place back in 1984, at the young age of 13, the entire building was covered with scaffolding. Over a five-year period, stonemasonry and sandblasting work was undertaken quickly, efficiently and at reasonable cost, and the House of Commons and the House of Lords continued to meet in this locus. There was no need to decant.
Those of us who were in the last Parliament, as many Labour Members were, had the personal experience of seeing the part of the building that we call the Elizabeth Tower being zoned off. The clock tower was repaired with minimal fuss. Yes, the repairs were completed a few years after the original timeline that had been set out, but it was repaired without causing any blockage between the Palace and the rest of the northern estate.
The House agreed to the renewal of the Victoria Tower, an even larger edifice. The parliamentary archives were shipped off to Kew and the building stands empty. It could easily be zoned off and refurbished. There is no need to do a full decant of this building—this building is so large that it can be zoned off over a period of years, and necessary urgent repair and remedial work can be undertaken.
The hon. Member for Caithness, Sutherland and Easter Ross (Jamie Stone) rightly referred to Holyrood and his own involvement in the building of the new Scottish Parliament—I am, of course, not blaming him for what happened. Lord Fraser of Carmyllie conducted the report into the catastrophic excess of costs spent on that building. It was budgeted at £45 million of British taxpayers’ money, but it ended up costing all of us almost half a billion pounds, as I am sure the hon. Member will remember. Lord Fraser’s report concluded, in good old Scottish, that everyone involved in that project said, “It wisnae me.” Nobody was held to account for that appalling overspend of taxpayers’ money for the Scottish Parliament building.
Jamie Stone (Liberal Democrat, Caithness, Sutherland and Easter Ross)
Lord Fraser conducted the Holyrood inquiry and I gave evidence to it. I did not say, “It wisnae me.” I am proud of what Lord Fraser said in his concluding remarks, because he said that I gave surprisingly honest evidence. I rest my case.
Alberto Costa (Conservative, South Leicestershire)
I welcome the hon. Member’s intervention and I am glad to hear him confirm that, indeed, “It wisnae me.”
The point remains that this country has had a problem with public sector building work. The Scottish Parliament building is a prime example and HS2 is another. I am not blaming MPs, Lords or House officials, but businesses out there are licking their lips about what will be the biggest building project in recent British history if we decide to do a full decant.
Markus Campbell-Savours (Labour, Penrith and Solway)
In around 2009, I hand-delivered a pre-qualification questionnaire to Parliament as the company I was working for at the time wanted to be a part of that bonanza. Many years later, as the hon. Gentleman’s colleagues are talking about these huge contingency plans, does he not recognise that the delay has made many contractors not want to work with us, and that they will probably be building a hell of a lot of risk into what they put in their estimates?
Alberto Costa (Conservative, South Leicestershire)
That may well be the case. However, 10 years ago, I and many colleagues were arguing, as the Father of the House said, just to get on with it and repair the building. It is sad to see that after 10 years we have simply not done that. I still do not understand why the Victoria Tower stands empty when that particular part of the building could be repaired.
I am mindful that others want to speak, but a couple of hon. Members have referred to this building representing the mother of all Parliaments. My concern is not so much that we remind colleagues that this is the mother of all Parliaments; my concern is that if we squander taxpayers’ money and we do a full decant, it will become the mother of all white elephants in British public building work.
Luke Charters (Labour, York Outer)
Given that the Opposition have, peculiarly, chosen this issue for an Opposition-day debate, I will start with the Conservative party. I thought its raison d’être was to conserve, but apparently not when it comes to conserving this place, the UK Parliament. The Leader of the Opposition called it akin to bankrolling billions to create a “net-zero Dubai hotel”, mocking efforts to restore this very place. I have been with the Public Accounts Committee to Buckingham Palace to see how the decisions that gripped the timeline and project management led to a successful restoration programme there. I have been underneath this building, metres below, and I thank the R and R team who do a wonderful job in explaining why Parliament needs restoring.
This issue was ducked by the Conservative party for years and years. In 2018, the Labour party backed a timely decant to allow essential restoration. Who voted against that? The Leader of the Opposition. Now, more than five years after that, Conservative Members come crowing about the cost of their own decision. This is just a wider problem of a failure to deliver infrastructure projects such as High Speed 2. We saw that with Crossrail, the completion of which was delayed, and even with a garden bridge. Now Conservative Members come here pointing the finger at everyone but themselves. I have heard many contributions from Conservative Members, but what has not been mentioned? An apology. Conservative Members have a pattern: destroy public services, let large projects spiral in cost, get obliterated in a general election, and never show even a modicum of humility. They really have learned nothing.
I am the son of a surveyor and joiner, and a fire safety officer—my mum. The safety of buildings is perhaps in my DNA, which is why I believe that the safety of the staff who work here—the Doorkeepers, cleaners, cooks and so on—should be central to our decision. I encourage hon. Members to go to the ticket office in Central Lobby, where a plaque commemorates the contributions of those who made this place. The safety of those who work in this place should never be debated and traded off.
I wish to touch on something important. In 1984, York Minster had a fire. I am proud that my dad was an apprentice joiner in the restoration work. We learned that timely decisions on decant were integral to that. I also want to touch on heritage skills, because my York Outer constituency will play a huge role in the restoration of this place. There is a centre of excellence for heritage skills in the grounds of York Minster, and there has been a revival of the 800-year-old tradition of apprentices living and working on the site. Up the road at York College in my constituency, stone masons learn their craft. It is one of the few places in the country to do that, and the pride of a stone mason is always seeing their mark left in the stone—a signature that will outlast them for centuries. That is a metaphor, if ever we needed one, for the generational impact of investing in vocational skills.
Hannah Spencer (Green, Gorton and Denton)
Green MPs think the motion is incredibly irresponsible, and I have heard some unusual and, quite honestly, dangerous suggestions from people who, with respect, I suspect have never picked up a screwdriver, yet who are apparently now experts in construction. Does the hon. Gentleman agree that we need more people from ordinary backgrounds and with those skills in this place? When I was working as a plumber, there is no way I would have advised a customer to keep spending eye-watering sums of money rather than just getting on with the job. We need to make these Benches more accessible for everyone.
Luke Charters (Labour, York Outer)
I hope the hon. Lady will therefore encourage her party to back the Milburn report, which will be transformative in bringing those vocational skills and opportunities to young people.
I will let other Members contribute, but I just wanted to touch on some recent visitors. Club Wilber, a local group of visually impaired children, visited Parliament just the other week. Their curiosity and fascination with this building was humbling. They saw things where they could, and asked questions where they could not. I will always remember when the children walked through the corridors just behind the Chamber. They were reaching for the MPs’ lockers and using their sense of touch to explore the immense history of this place.
Rebecca Smith (Conservative, South West Devon)
Will the hon. Gentleman give way?
Luke Charters (Labour, York Outer)
I will not just because of the other Members wanting to speak.
We must remember the visitor experience of those disabled children from my constituency, and the thousands who visit here every month—that is the point that my hon. Friend the Member for Penistone and Stocksbridge (Dr Tidball) made so well. There is no price too high when it comes to accessibility for some incredibly inspirational children to this place.
Let me end by praising the Prime Minister, who took the decision to lift part of the Executive branch to No. 10 North. That really fosters a conversation with the public about how we can share debate across the country. As we look to the R and R of this place, I encourage conversations so that we can have further debates closer to communities such as mine. That is precisely our ambition with rewiring the state. This is the home of our democracy, and we must look after it.
Nigel Huddleston (Conservative, Droitwich and Evesham)
I disagree with some of the things that the hon. Member for York Outer (Mr Charters) just said, but I agree vehemently with his points about heritage skills. I will not repeat his points, but I agree with them completely.
It is clear that there is broad agreement across the House that the Palace of Westminster must be restored. The question before us is not whether that work should take place, but how we deliver it in a way that protects a historic building while providing value for money for the British taxpayer. As a former Heritage Minister, I have a particular passion for protecting our historic built environment. Parliament is one of the most recognised symbols of our democracy. It is a UNESCO world heritage site and a building entrusted to us by previous generations to be preserved for those who come after us. For centuries, it has been at the heart of our national life, witnessing some of the most significant moments in British history.
It is precisely because this institution matters so much that we must get its restoration right. It is therefore worrying that no one appears to be truly in charge. Cost estimates continue to rise and timelines continue to slip, yet accountability remains fragmented across committees, boards and delivery bodies—I think we have had five boards and counting. If everyone is responsible, we know that no one is responsible, so governance is key. Especially at a time when we are asking families to make difficult financial decisions, Parliament cannot except itself from the standards that it expects of every Department and every household budget. Every pound spent here is a pound that cannot be spent elsewhere. We must therefore ensure that the process is streamlined wherever possible, that unnecessary costs are eliminated and that savings are secured without compromising safety.
The Notre-Dame restoration has been commented on several times already today. It cannot be directly referenced—it is not directly the same thing—but there are many lessons to be learned from its restoration, particularly in how the French had a sense of urgency, a clear scope, decisive delivery and clear governance. After the 2019 fire, they were able to restore Notre-Dame and reopen it in just over five years, at a cost of about £846 million. It did not seem to have layers of billions of pounds of contingency funding and management costs, as our plans do. That is an important point.
What is it that others are able to do overseas that we are getting wrong here? We need to genuinely look at where we can learn. The costs are truly astronomical, ranging from £11 billion to £39 billion. Why is so much of the money being allocated to contingency, planning and project management? Why is so little of the total proportion going to actual, physical labour on construction and actual building materials? We must carefully consider those things.
Several hon. Members have said today, “Oh, these big infrastructure projects and big Government projects overrun all the time.” No, they do not. I am very proud that I led the delivery of the Commonwealth games. That was a different project, but it was a major project of £750 million involving construction and the building of a stadium and a new aquatics stadium. The reason why I reference that is that not only did we deliver on time, despite construction happening during the pandemic, but we delivered under budget. The lessons from that are important, because we had clear governance and accountability, a sense of focus, a fantastic team and, really importantly, rigorous discipline in the oversight of contractors. We can deliver projects on time and on budget.
This debate is not about whether we restore the Palace of Westminster—of course we must. It is not about whether we preserve one of the great democratic institutions—of course we should. The question is about how we do so with the discipline, accountability and value for money that the British public expect from us all. Let us ensure that we make the Palace safe, preserve it for future generations and deliver a restoration programme that is affordable, respectful of the British taxpayer and planned with the discipline and rigour worthy of the institution that it seeks to protect.
Caroline Nokes (Conservative, Romsey and Southampton North)
Order. With a four-minute time limit, I call Dr Jeevun Sandher.
Jeevun Sandher (Labour, Loughborough)
This place is not merely a place in which we live or represent others; it is the physical manifestation of what makes this country great—indeed, the greatest country that has ever been. This place is where we expanded voice, and it is where different people were represented in the making of powerful decisions that not only ensured they had political representation, which they did, but set the stage for the industrial revolution, and therefore the greatest expansion in human dignity and welfare there has ever been. We also know that in this place—in this building—we must not only preserve the values that we hold dear for future generations, but ensure that the building physically remains. As we all accept on both sides of the House, the building is not physically where it needs to be.
When I say this place is a physical manifestation of what makes this country great, I refer to the fact that it was first built by one of the sons of William I, and it was where we saw the Earl of Leicester call his first Parliament in Westminster. It is where we then saw a king who tried to implement his absolutist monarchy be not only rejected by MPs, but sadly sentenced to death. It is where we saw the passage of reform Acts that ensured the representation of people and their voices in the making of decisions. This place does not just represent those events; it is where they happened. This place—and this country— was the first on Earth to see sustained economic growth, precisely because of the ways in which power spread from this area and ensured that policy was made in the interests of people outside a very narrow and select few.
We also know that this place is falling apart. We know about the fire risks, and we know about the risks to the electrics and the leaks, because we see and experience them. We also know about falling masonry. I heard of one colleague who had some masonry fall on their staff member’s desk. Of course, had it fallen somewhere different, that may have had a rather more tragic outcome. That is what we are here to fix.
I believe that everyone across the House acts in good faith in seeking to not only preserve the physical institution, but ensure that our values are preserved for future generations. Others may say that the Conservatives are cynical, having not dealt with this issue during 14 years in office. Some say they are now cynical in knowing that delays will cost us money. Some may say they are cynical in trying to undermine the good faith of those who are trying to renew this place for future generations, by making that look short-sighted. Some would say that the Conservatives are cynical, but I would not—I will leave that to other hon. Members.
I remember how I felt when I entered this place for the first time—it was not actually when I became an MP, but when I was 20 years old. I did not have a beard back then, so a lot has changed, but my reverence for this place never has. I know this is a special place that represents so much more than the building. It represents the values we hold dear, and the values that we have given to not just our people but the entire globe.
Wendy Morton (Conservative, Aldridge-Brownhills)
There is no doubt in my mind that, right across the House, we all recognise the historic and democratic importance of this building, as well as the need to ensure that it is safe for everyone who works here, and for everyone who visits. We have a duty to preserve this place for future generations.
We also have a duty and responsibility to our constituents—the people whose taxes will pay for this work. For people in Aldridge-Brownhills, the sums being discussed today, which range between £11.1 billion and £39.2 billion, are absolutely eye-watering. They rightly expect us to ask questions about how their hard-earned money will be spent. That is why over recent months, not just today, I have tabled a series of written questions to the restoration and renewal client board. I want to focus on three issues arising from those answers: the scope of the programme, the initial expenditure and the accountability for delivery.
My first concern is whether we have properly examined a more affordable approach.
I asked the client board whether a reduced programme focused on only the essential safety and resilience changes had been fully costed. The answer confirmed that no alternative scope had been costed to the same level of detail as the preferred scheme. How can that be the case? Surely that estimate matters. If we are to be able to make informed choices and comparisons before committing billions of pounds, we need to understand what is essential, what improvements are proposed alongside it, and what each approach would cost. I recognise that the Leader of the House is not in his place at the minute, but I would be grateful if he could explain to me how Members are expected to make an informed decision on value for money without that information.
Secondly, there is the proposed £3 billion initial works package. I specifically asked how much of that expenditure could become sunken costs if Parliament subsequently changed its plans. The answer did not give me a figure. The Public Accounts Committee has since warned that once the initial package is approved, it will be extremely difficult and costly not to proceed with the entire project. That is a significant warning, so we need to understand how far the first decision will, in practice, commit us to the next. What expenditure would be recoverable, what would be lost, and what choices would remain open to a future Parliament?
Thirdly, there must be accountability. When I asked about individual enhancements such as new visitor facilities, the proposed visitor plaza, relocating the Education Centre and so on, the client board confirmed that
“there are no standalone business cases for individual scope elements within the Palace”.
When I asked about construction risks, it acknowledged that
“some…are not yet fully reflected in the quantitative modelling”.
Those answers reinforce the need for scrutiny before further commitments are made. Who will take responsibility if costs increase, how will Members scrutinise changes, and what action will follow if delivery falls behind?
I recognise that delay has a cost. I also recognise the work undertaken by staff to keep this building safe and operational, but the answer must be a restoration project with clear priorities, a credible timetable and proper financial control. When we are spending money on Parliament itself, we should be setting that example.
Bambos Charalambous (Labour, Southgate and Wood Green)
In this debate, we have heard many wise words from Conservative Members. It is just a shame that they did not voice those wise words when they were in power.
The decision to decant and get on with the works was taken on 31 January 2018. A similar resolution was passed in the House of Lords. I and other Members who were in Parliament then voted; it was a cross-party vote, not a whipped vote, because it was a matter for the House. In that debate, the then Leader of the House, Dame Andrea Leadsom, spoke about the urgent need for restoration and renewal works to begin because of, among other things, the
“hotch-potch of pipework and wiring”—[Official Report, 31 January 2018; Vol. 635, c. 880.]
in the basement of the Palace, the risk of fire and the need for asbestos removal. A number of Members who are on the Opposition Benches today took part in that Division and voted in the way they wanted to vote. At the time, the cost of doing the works was around £3.5 billion. Since then, there has been a 36% increase in the consumer price index—that is inflation alone. Dame Andrea Leadsom said at the time that the debate we were having, on 31 January 2018, should have taken place 40 years earlier.
Following the two votes that we had, in the Commons and in the other place, an Act was passed: the Parliamentary Buildings (Restoration and Renewal) Act, which set up a Sponsor Body to get on with the works. Unfortunately, the Sponsor Body did not do its job, and its powers were then subsumed back into Parliament. The restoration works have a chequered past, and it is incumbent on all of us to make sure that we start those works as soon as possible, progress them and get things done. Other Parliaments seem able to do this: Canada has decanted its Parliament, which is still undergoing restoration and renewal works; the Dutch Parliament has been decanted, and works are under way; the Austrian Parliament has already done its works.
The Public Accounts Committee’s report on the cost of these restoration works says that the cost of delaying would be about £420 million each year. Kicking the can down the road is not an option. That will cost £1.5 million a week, and that is unacceptable. We need to get a move on, and we need to get the works done as soon as possible.
As to what those works will be, I do not know whether it was by fortune or design, but there is a stall in Portcullis House that lists all the information. If people want to know what the £3 billion will go to, there is a phase 1 sheet that lists all the works, and I encourage people to have a look at it. The Father of the House, the right hon. Member for Gainsborough (Sir Edward Leigh) said that we need to get a move on, and we do, but we will only be able to do so if we start phase 1 of the works as soon as possible. There will be a vote in this House on 8 December, as the Leader of the House has said. I encourage everybody to take part in that and to vote the way they want to. It should not be a whipped vote; we should all have our say in how we want the future of Parliament to progress.
Julian Lewis (Conservative, New Forest East)
Although he is no longer in his place, I put it on the record that I certainly did not put my name to this motion with any inclination to embarrass the Leader of the House. I think he is very good in his role, and I am sure he is pursuing this matter with his customary energy and vigour. What I am concerned about, as I have said in a number of interventions, is the sheer scale of expenditure envisaged and the lack of clear direction, both in the control of the project and in understanding what the objectives are, namely whether it is primarily and almost exclusively to make the building safe or whether it is to turn it into something else. If we do not know where we are going, we cannot chart an economically viable path to our destination.
I detected one area of agreement, however, when the Leader of the House described the network of committees and bodies that have been involved hitherto as “spaghetti”. I entirely agree, and we heard that point from my hon. Friend the Member for Droitwich and Evesham (Nigel Huddleston). I think W. S. Gilbert put it very well in “The Gondoliers”:
“When everyone is somebody, then no one’s anybody.”
The truth of the matter is that when everyone is in charge, no one is in charge.
We need to bring into this process a single directing unit with the power to see it through—if not an individual, a very small number of individuals. If we carry on as we are, with these large bodies in some sort of kaleidoscopic combination of pretty patterns that leads to no discernible progress other than an ever-increasing bill potentially running into the billions, we will not only expose the House to physical danger, but expose Parliament to public contempt. There is a real risk in spending billions on ourselves in this way, no matter how worthy the cause, that the public will not tolerate something that is grossly uneconomic.
Marie Goldman (Liberal Democrat, Chelmsford)
I just want to ask the right hon. Gentleman a quick question. He talks about spending money on ourselves. Does he recognise that it would be spending money not only on democracy, but on the people who work here, who deserve a safe environment to work in?
Julian Lewis (Conservative, New Forest East)
Yes, I do recognise that, but I point out to the hon. Lady that having a good cause—a vital project, such as stopping this building burning down—is not a justification for spending possibly two, three, four or five times as much on prevention as could be spent to achieve the same objective. The worthiness of a cause is not a justification for spending 200%, 300% or 400% of what competent professionals should be able to budget for to carry out a project efficiently.
In the short time that remains to me, I want to revert briefly to the question of the options and the question of decanting. I am in the same position as the Father of the House: I am unlikely to be affected personally by whatever arrangements are made for decanting. However, if the Houses of Parliament are emptied of MPs for 20 years—although it will probably not be 20 years, but 30 or even more—two, three or four generations of MPs will be out of here. They will be put in modern facilities, and when the time comes for them to return, they will not want to do it. If this building is indeed the heart of our parliamentary democracy, and if we wish to preserve it and prevent it from becoming nothing more than an over-expensive museum to the sort of political system that we used to have, we must ensure that MPs remain in at least partial occupation of the building, whichever option we finally choose.
Markus Campbell-Savours (Labour, Penrith and Solway)
I support the Government’s approach. I speak as someone who approaches major public spending programmes with a healthy degree of scepticism and who spent much of his pre-political career planning and delivering electrical installation works in period buildings across central London. I have looked at the evidence, and it is clear to me that the greatest risk to the taxpayer is not action, but delay.
We know the condition of the Palace. We have heard that since 2016 there have been 12 asbestos incidents, 19 stonemasonry incidents and, importantly, 36 fire incidents. We know that key services fail regularly. We know that the current patch-and-mend approach is costing about £1.5 million every week and that the figure is forecast to rise to £2 million a week. Most importantly, we know that every year for which we defer a decision costs money. Continued delay adds about £70 million in direct maintenance and option planning costs, alongside between £250 million and £350 million in construction inflation. That is not caution; it is a very expensive form of procrastination.
The Opposition seem to believe that these concerns are an argument for slowing down decision making yet again. We have seen that approach from them before, including in new nuclear capacity, when years of hesitation left us needing to import more energy at a higher cost. The “do nothing” brigade invariably presents delay as the cautious option, but in reality it is often just storing up bigger bills for the future.
We have been debating variations of this issue for years. During that time, the condition of the building has not improved, the bills have not become smaller and the risks have not diminished. That is why I think that the Government are taking a sensible approach. What is being suggested is cracking on with a capped first phase, stronger financial controls, greater parliamentary oversight, annual scrutiny and further reporting before future decisions are taken.
There is another aspect that should not be overlooked, which is that this should not be seen simply as a project for Westminster. The restoration of the Elizabeth Tower involved specialist skills drawn from across the United Kingdom. Indeed, a company from my own county, the Cumbria Clock Company of Dacre, near Penrith, played a central role in the conservation and restoration of the Great Clock mechanism itself, painstakingly restoring more than 1,000 components of what is arguably the most famous clock in the world. That is a reminder that projects such as these support highly specialist skills and expertise far beyond London. This programme has the potential to support thousands of jobs, apprenticeships and traditional crafts in every nation and region of the country.
Jamie Stone (Liberal Democrat, Caithness, Sutherland and Easter Ross)
The point is extremely well made. I am sorry to talk again about the building of the Scottish Parliament, but a decision was taken to use suppliers of all sorts of building materials from all parts of Scotland, and that was extremely well received by the people of Scotland. Secondly, one should always remember that—as I think the hon. Member is saying—all the money that is spent boosts the economies of various parts of the UK, so let us hope that the money is spent all over the UK.
Markus Campbell-Savours (Labour, Penrith and Solway)
The hon. Member makes a very good point. I can envisage a different debate in the future, when Members will come to the House and ask, “How do the businesses in our constituencies benefit from a project of this scale?”
The National Audit Office says there is sufficient information to move forward, as does the Public Accounts Committee. At some point, prudence stops being prudence and starts becoming procrastination, and I believe that point has now been reached. For that reason, I support the Government’s approach and oppose the Opposition’s motion, which reminds me of a grumpy old man telling his long-suffering wife that their 1990s MFI kitchen is fine and just needs a lick of paint and some new knobs. I met a few of them during my career, and I have seen a few of them in the Chamber today.
Andrew Murrison (Conservative, South West Wiltshire)
I sympathise with the frustration of the Leader of the House, which was evident in everything he said. This is not an easy matter—if it was, we would have dealt with it by now. I loved his term “spaghetti governance”, because that lies at the heart of where we are. The situation has been a disgrace over many years, and my plea is to have a single accountable officer who is responsible for what is going on at the moment, for phase 1, on which we will be voting shortly, and for the definitive project in due course. We cannot demand of other Government Departments and agencies the financial discipline that we are not prepared to apply to ourselves.
The Leader of the House said that we are the custodians of the seat of democracy, and he is absolutely right. But the exercise of democracy is a darn sight more than simply a stack of limestone, however exquisite; it is the functioning of democracy. It is what we do here, and what we must not interrupt in the course of the refurbishments. Unfortunately, confidence in democracy is low and confidence in ourselves is low, and I fear that the public simply will not understand why we are contemplating spending the spectacular sums that have been cited on ourselves. That is how it will be seen, regardless of whether that is fair or not.
I have two tests, which I think are reconcilable. First, we must keep this place open for business. It is more than a pile of a bricks; it is the living, vibrant cockpit of our democracy. If it closes or decants, I genuinely fear that we will never return, and we will be spending all this money on what will amount to a museum—a white elephant. We can plan essential works around parliamentary business, not the other way around. We can do that with reasonable adjustments, such as canning September sittings and shifting the revising Chamber elsewhere, if we really must. In my view, a full decant is out. The EMI+ option is not great, but it is preferable. However, I am tempted by the suggestion from my right hon. Friend the Member for North East Cambridgeshire (Steve Barclay) that we could have the midway option of a temporary and time-bounded decant.
Secondly, we have to keep this affordable. The public sector has a tradition of gilding the lily, and I fear that may be the case here. We must fix the basics, and we must do so quickly. Let us get on with it and make a decision beyond phase 1 now, not in 2030. That is where the cost of delay lies, not in the reasonable acquisition of details on the proposed spend, as has been suggested today. Let Notre-Dame and Buckingham Palace, which were delivered on time and on budget, be the guide, not the Elizabeth Tower and the disastrous Peers’ Entrance. We need to take a view on some of the proposals being made on net zero and exquisite energy-efficiency in an ancient building, coffee shops, educational facilities and visitors’ centres. We must not make the excellent the enemy of the good.
Rebecca Smith (Conservative, South West Devon)
I appreciate the opportunity to speak, having listened to this very important debate, particularly as I am one of the 2024 Conservative intake. I am a historian by nature, and I came here as an 18-year-old and fell in love with the place. On the point made by the hon. Member for York Outer (Mr Charters), if we cannot bring young people into this building for the entire length of time of the proposed decant, we will be wrecking the opportunity for entire generations of young people to be inspired by the Palace of Westminster and the Parliament that sits within it.
We Conservatives are not saying that restoration should not happen—far from it. This building is something we value, and we recognise that it needs to be improved and fixed, but we are against the renewal process, which will effectively introduce to the building architectural features that we will not get to use for 30 or 40 years, by which point they will be out of date. We will be setting up future Members of Parliament to be embarrassed by what we decided to go forward with. I want to say, as one of the 2024 intake, that it still remains the case that I value the heritage of this place and want to maintain it as much as possible, but I also want to keep access to it.
I also want to make a point about the Christian heritage of this building. The Chapel of St Mary Undercroft is not mentioned once in the 125-page report, and there are some artist’s impressions that call into question what will actually happen to that unique and important part of the building. Worship takes place there several times a week, and it is an important part of the life of the Palace of Westminster. Would the Leader of the House reassure Members, when we come back on 8 December, where that worship will take place, and what will happen to the chapel and, indeed, to the Christian heritage of the building as a whole? Mr Speaker has said that
“Parliament is a veritable trove of our Christian heritage”,
and it is up to us to ensure that we maintain that.
Furthermore, there are questions about the ceremonial and remembrance work that we do. Ultimately, the State Opening of Parliament is grand because it is here. I would be interested to know what will happen to that. I was with Baroness Fookes from the other place yesterday, talking about the importance of remembrance, and she highlighted the turning of the page of the remembrance books that takes place in the Royal Gallery, and we know the turning of the page takes place here every week as well. Where will that sort of remembrance and commemoration take place if we are decanted into Richmond House or the Queen Elizabeth II centre?
We are Parliament, and it is up to us to maintain the heritage of our country. If we cannot do that because we are, in effect, sitting in a conference centre for decades, I would love to know how we can ensure that we continue to play that role.
Caroline Nokes (Conservative, Romsey and Southampton North)
I call the shadow Minister.
John Lamont (Conservative, Berwickshire, Roxburgh and Selkirk)
I thank the shadow Leader of the House for opening this debate and Members from across the House for their thoughtful and considered contributions. We have heard almost 20 speeches.
The restoration and renewal of this place—the home of British democracy, the mother of Parliaments—was never going to be easy.
Gareth Snell (Labour/Co-operative, Stoke-on-Trent Central)
Will the hon. Gentleman give way?
John Lamont (Conservative, Berwickshire, Roxburgh and Selkirk)
I am going to make some progress, if I may.
Anyone who has ever embarked on a renovation of their own home could have told us that this was never going to be easy. The scale of the works is clearly different, but the emotions of a home renovation are similar. The excitement and enthusiasm soon give way to the frustration of delays, the irritation of cost overruns and the mounting desire just to get it over with. Most home owners get through it, because they see progress and know that the end is in sight. We do not have that advantage. The renovation of Westminster has achieved little to date, with many billions and decades to go, so we must get this right from now—from this moment. We cannot allow this project to become a symbol of the failure of the political class to get things done, which it will if it continues on this path.
Marie Goldman (Liberal Democrat, Chelmsford)
Much has been made of the first phase of works, and the hon. Member talks about how difficult it is for home owners to do projects in their own home. Does he agree that a lot of the work that goes into someone redecorating their own home comes from the preparatory work? We need to get that right, so does he also agree that the £3 billion for the first phase of works is really about getting some of the prep work right?
John Lamont (Conservative, Berwickshire, Roxburgh and Selkirk)
The hon. Lady makes a fair point, but the problem is that we do not know what the project is yet. It is not clearly defined, there is no clear timescale, and the cost is not clearly capped. If I am renovating my home, I know how much I can afford. We have responsibility for how much this project is going to cost on behalf of all British taxpayers.
George Freeman (Conservative, Mid Norfolk)
For the record, I have consistently voted for a full decant, because I believe we need to sort this out and grip it. Would my hon. Friend agree with me that the test is not just whether we can get the maintenance right, but whether we, as custodians of this building, can work as a Parliament with clear governance and clear direction, not changing our mind and scoring points, and get this part right? I fear at the moment that the public will see what has gone on and worry that we are going to kick this down the road, spending money and wasting money. We need to get it right once, properly—not by designing the most expensive building in the world, but by making it safe and workable for the next generation.
John Lamont (Conservative, Berwickshire, Roxburgh and Selkirk)
My hon. Friend makes an important point. Of course, accountability is the key, and I will come to that a bit later.
As the Father of the House, my right hon. Friend the Member for Gainsborough (Sir Edward Leigh), highlighted in his speech, the lack of clarity is concerning. When a hospital needs a new wing, we expect a clear budget. When a school needs rebuilding, we expect a timetable. Yet so far, when Parliament has needed restoring, it has been a struggle to get either. Of the options outlined to date, some will be more palatable to the public than others, but we surely cannot agree to an open-ended programme of works that could cost £39 billion and last 61 years.
That point was by made a large number of right hon. and hon. Members, including my right hon. Friends the Members for Gainsborough and for North East Cambridgeshire (Steve Barclay), my hon. Friends the Members for South Leicestershire (Alberto Costa) and for South West Devon (Rebecca Smith), my right hon. Friend the Member for South West Wiltshire (Dr Murrison), my hon. Friend the Member for Droitwich and Evesham (Nigel Huddleston) and my right hon. Friend the Member for Aldridge-Brownhills (Wendy Morton). I recently met a group of high school students from the Borders who were here on a tour of Westminster. They would be long retired by the time this project finished, and that £39 billion cost would cover their local council’s budget for all the years in between.
We have an obligation to ensure that these buildings stand for future generations, but we should not be passing them a bill of this size for that privilege. Despite what the Leader of the House claimed, we all understand that there must be investment to make the estate safe, but the spending must be made with restraint. If we agreed to that £39 billion budget and a 61-year project, tourists would add Westminster scaffolding to the list of famous sites to visit. The scaffolding itself may even get listed status!
No, the renewal works must not drag on for decades at ever-escalating costs, otherwise the public will understandably ask why we can find tens of billions of pounds for improvements to the place where politicians work, while telling communities across the country that money is too tight to improve necessary services in the places where they live. While recognising the need to make buildings safe and accessible—a point made by the hon. Member for Penistone and Stocksbridge (Dr Tidball)—the project must demonstrate the fiscal responsibility that we seek of others. The restoration of Westminster should meet the same financial standards that any home renovation seeks. It must stick to its budget, provide good value for money, deliver a functioning building and preserve this home of democracy for future generations.
The excellent Public Accounts Committee report published this month laid out in great, excruciating detail the scale of the problems. None of us can say we were not warned of what is going wrong with this programme. We do not yet know the true cost, the duration, the scope or who leads it. As the shadow Leader of the House, the right hon. Member for Hereford and South Herefordshire (Jesse Norman), succinctly put it:
“No single entity is empowered to make the difficult trade-offs needed between cost, scope and timetable. Ask who is in charge, and the correct answer is: no one.”
All the boards and committees set up to manage the programme are simply, as the Leader of the House highlighted, the spaghetti junction of accountability. That is not acceptable.
The Public Accounts Committee also makes it clear that MPs have not been properly engaged on the scope and purpose of the programme. By June, fewer than half of sitting MPs had engaged with the project team, and the Committee questioned the quality of that engagement. If I may say so, the intervention by the hon. Member for Bury St Edmunds and Stowmarket (Dr Prinsley) highlighted that perfectly. He rightly highlighted some of the failures of the building for his staff—there is no heating, it is too hot in the summer—but the building he identified, 1 Parliament Street, is outwith the scope of these works. These problems will continue and they highlight the inadequacy of much of the engagement that has already taken place.
We are being asked to make decisions that could cost British taxpayers billions of pounds without a clear picture of what it is for. The public have every reason to question what it would be for. As others have noted, a new Peers’ Entrance cost £9.6 million—almost £10 million on a door that has struggled to open properly. I dread to think what will happen when we get on to the windows and the roof. Even the most basic of home renovation projects seeks to make a house easier to live in. We appear to be embarking on work designed to make it even harder to be here.
A number of Members pointed out that we also need to recognise the cost of doing nothing, which is around £1.5 million a week to maintain these buildings. Every year of delay could add up to £420 million to the overall cost. That is a serious argument for action, but the plan must be the right one—a point that was well made by the Chair of the Finance Committee, my right hon. Friend the Member for North East Cambridgeshire. We are calling for a fundamental rethink, and an independent review to be completed within 90 days: a short, focused exercise under the joint leadership of the Speakers of both Houses, with cross-party support.
As the shadow Leader of the House outlined, the review’s objectives should be to put before Parliament a clear budget, scope and schedule for a scaled-back programme of work focusing on the primary job: urgent safety improvements, followed by manageable restoration projects, each with defined objectives, specified budgets and explicit parliamentary authorisations.
This place is the home of British democracy. Taxpayers who have renovated their own homes are prepared for the challenges; they have all had a builder come back to them and say, sheepishly, “Bad news, I’m afraid, Mr Lamont.” But what they will not, and should not, tolerate is a project beginning, continuing and ending with bad news. We must get this right now, so that that does not happen. I urge the House to support our motion.
Mark Tami (Labour, Alyn and Deeside)
It is a pleasure to close this debate on behalf of the Government. I am delighted to see so many Members on the Labour Benches who are interested in R and R. It is hard to believe, but it has been six and a half years since I was last at the Dispatch Box. I was in opposition, and it was on this very subject—good things come to all who wait. At that time, I accused one Jacob Rees-Mogg, late of this parish, of wanting to kick the can down the road, as many Members have said today.
As a former Prime Minister once said, “Nothing has changed.” Nothing has changed because we are here again with the Conservatives making exactly the same points. The shadow Leader of the House, the right hon. Member for Hereford and South Herefordshire (Jesse Norman), wants us to rip everything up and start all over again, in pursuit of a mythical option that will somehow take far less time and cost far less money, without any explanation from the Opposition of how that is going to happen.
I am going to praise the right hon. Gentleman. He is famed for his works on Edmund Burke and Adam Smith, but I was drawn to one of his earlier works, entitled “Breaking the Habits of a Lifetime”—something I am afraid he has not followed today by once again failing to tackle the hard decisions. I will be honest: I thought I had hit comedy gold when I discovered another work entitled “Stand Up Straight and Sing!”, only to find out that it was actually by an American opera singer of the same name. I am sure that one day the right hon. Gentleman will get his wish, and Vogue will come calling.
We have had a lively debate today, and I hope that the Opposition have found that this was a good use of their Opposition day, ahead of the main debate. I am not sure whether Opposition Members actually thought this was a good idea. At its heart, restoration and renewal is a House matter. The Government have done the responsible thing and waited for the reports of the National Audit Office and the Public Accounts Committee, which agree that the House now has all the evidence it needs to move forward. That is why we have tabled a motion and will allow time for a full and informed debate on the matter on 8 December. For the avoidance of any doubt, that is a Tuesday—the shadow Leader of the House obviously thought otherwise.
There have been many contributions today. I would like first to mention the Liberal Democrat spokesman, the hon. Member for Newbury (Mr Dillon), on what is, I think, his first outing. I agreed with almost everything he said. He was very good. My hon. Friend the Member for Blaenau Gwent and Rhymney (Nick Smith) pointed out the dangers of make do and mend, and said that that was not an answer.
As the Father of the House pointed out, we have sparred on a number of occasions. He is very clear in his view. I remember him telling the Sponsor Body that because it had come up with a decision that certain people would not like, it would be abolished—and he was right. That is part of the problem: the fact that we have had this constant chop and change all the time.
My hon. Friend the Member for Bootle (Peter Dowd) made some very important points and said that it is clearly time for us to actually take the decision.
The right hon. Member for North East Cambridgeshire (Steve Barclay), the Chair of the Finance Committee, whom I do not see in his place at the moment, gave us a lot of figures. He said that we should decant for four years—based on what, I don’t quite know. Again, he did not actually come up with a solution.
In a powerful contribution, my hon. Friend the Member for Penistone and Stocksbridge (Dr Tidball) talked about disability access to this House and, indeed, the importance of staff benefiting from that. As someone who looks after office accommodation for Government Members, I am sure that Members will say—
Marie Tidball (Labour, Penistone and Stocksbridge)
Will my right hon. Friend give way?
Mark Tami (Labour, Alyn and Deeside)
I will indeed.
Marie Tidball (Labour, Penistone and Stocksbridge)
I want to thank my right hon. Friend for setting an example to this House when I was first elected and ensuring that I got an accessible office that was close to the Chamber as soon as I possibly could. It made a great difference to my ability to settle into this House and do my job for my constituents.
Mark Tami (Labour, Alyn and Deeside)
I thank my hon. Friend very much for that intervention. She identified problems that many of us probably did not think about, such as where the lights and door handles are fitted. It took me a year and a half to get a door changed in Portcullis House, which is ridiculous.
The hon. Member for South Leicestershire (Alberto Costa) wanted no decant whatsoever. My hon. Friend the Member for York Outer (Mr Charters) again pointed out the cost of delays, and the great opportunity for apprenticeships that this programme will deliver. The hon. Member for Droitwich and Evesham (Nigel Huddleston) talked about the importance of heritage; my hon. Friend the Member for Loughborough (Dr Sandher) spoke about the importance of heritage, too, as well as the risks around the project. The right hon. Member for Aldridge-Brownhills (Wendy Morton) talked about the cost of the project.
My hon. Friend the Member for Southgate and Wood Green (Bambos Charalambous) reminded us all of the vote in 2018. We are now in 2026—it is a bit like “Groundhog Day”, isn’t it? Here we are again, rather than actually getting on with it.
The right hon. Member for New Forest East (Sir Julian Lewis) spoke about the importance of keeping the building safe and the importance of a good governance structure, which I accept is a point a lot of Members have brought up today. It is certainly something that we need to get right.
My hon. Friend the Member for Penrith and Solway (Markus Campbell-Savours) talked about his own experience in major construction projects and, again, spoke of the dangers of delay. The right hon. Member for South West Wiltshire (Dr Murrison) also talked about the governance structure, and said that we could somehow do everything without the September sittings, which, if I am brutally honest, I am not convinced about. The hon. Member for South West Devon (Rebecca Smith) also spoke about the importance of heritage. We should never forget that we are the custodians of this building, and we will pass it on to the next generation.
We have heard the usual rhetoric from the Opposition Benches today. However, we cannot live with another decade of delay and another review. If we are honest, we actually knew about these problems 70 years ago— I did not, because I am not quite that old, but a lot of these problems were known about—and we did nothing about them.
Pausing this programme is not the frugal choice. The act of merely propping up the estate costs the taxpayer £1.5 million every week, and that figure will rise to £2 million, which is a point a number of Members made. Every year of dithering adds up to £420 million to the lifetime costs of the programme.
We have been around this track before. We have debated it, redebated it, picked and unpicked options for over 10 years. I seem to recall that the Conservatives were in government at the time. Meanwhile, the risk to this building will not wait for another review cycle. Members of this House are entirely right to demand tighter governance and a relentless approach to cost control, but there is nothing stopping us making progress while we continue to improve the way that the programme is run and seek cost reductions ahead of the 2030 decision point.
The motion that the Government have tabled for debate next month will build on the momentum of the programme through an initial package of works with a capped spending profile, narrow the options under development to refocus the programme and bring immediate cost savings. It will require a thorough reassessment of the programme’s governance ahead of a final decision by the Houses in 2030. I urge the House to reject the Opposition’s motion and support the Government’s amendment.
Question put (Standing Order No. 31(2)), That the original words stand part of the Question.