Restoration and Renewal Client Board

House of Commons, 26 February 2026.

Client Board: Progress

Charlie Dewhirst (Conservative, Bridlington and The Wolds)

What recent progress the Client Board has made in its work.

Nick Smith (Labour, Blaenau Gwent and Rhymney)

The Restoration and Renewal Client Board has recently published a report providing costed proposals for the R&R programme and a recommended way forward. The key recommendation is to commence a phase 1 works package, including enabling works and the preparation of temporary accommodation, which includes a long-term resilience Chamber. It has reduced the number of delivery options from four to two, with a final decision on a preferred option required by 2030. The next step is for parliamentary debates to be held so that Members of both Houses can consider the client board’s recommendations and decide how to progress. The R&R team holds regular briefings, tours and detailed Q&A sessions, which the hon. Gentleman may find of interest.

Charlie Dewhirst (Conservative, Bridlington and The Wolds)

The London 2012 Olympics took seven years to organise and cost £7 billion. The World Trade Centre rebuild in New York took seven years and cost $3.9 billion. The restoration of Notre Dame cathedral in Paris took less than five years and cost less than €1 billion, yet here we are, with the cheapest option available to us to spend £16 billion and move out for 24 years. I am sorry, but that really does stink. We need to look again at the entire proposals for the restoration and renewal of this place. Restoration is fine, and we should all operate in a safe workplace, but I ask the hon. Member to go back to the board and look again at this entire proposal.

Nick Smith (Labour, Blaenau Gwent and Rhymney)

I agree with the hon. Gentleman that we should make much faster progress on this project. However, he talks about Notre Dame, which has a much smaller footprint than our Palace of Westminster. The bulk of the construction costs relate to the replacement and upgrade of mechanical power, water and heating infrastructure, improvements to fire safety, and the controlled management of asbestos and repaired stonework. Not enough has been invested in our palace over the years, and much more needs to be done. This needs to be done at a good speed, but I accept his point. Let us try to take Members of both Houses with us.

Palace of Westminster: Major Works

Meg Hillier (Labour/Co-operative, Hackney South and Shoreditch)

What its planned timetable is for starting major works on the Palace of Westminster.

Nick Smith (Labour, Blaenau Gwent and Rhymney)

The Client Board’s recent report recommends a way forward for restoration and renewal. It contains phase 1 works, including seven years’ foundational works for the full programme. These preparatory works can begin once we have approval from both Houses. A final decision on the preferred delivery option is required from both Houses no later than 2030. The main R&R works could begin in 2032.

Meg Hillier (Labour/Co-operative, Hackney South and Shoreditch)

In modern times, this issue has been discussed since 2016; we are on our 10th anniversary of discussing what has actually been an issue for 40 years. I disagree with the hon. Member for Bridlington and The Wolds (Charlie Dewhirst) about going back to the drawing board again. Does my hon. Friend have any idea of when the vote will be? If it is in 2030, that will be after the next election. I can see the same old arguments about having to revisit this being rehashed again and again, while the building remains riddled with asbestos and at risk of fire. Frankly, once the works begin, my staff and I will no longer be in the building because of safety issues.

Nick Smith (Labour, Blaenau Gwent and Rhymney)

I wholeheartedly agree with my hon. Friend. She is right to say that we must make progress, and we now have the costed proposals in front of us. The work is necessary. The home of our Parliament is not only an iconic building, but a UNESCO world heritage site. We currently spend £1.5 million a week on maintaining and repairing the Palace, and every year of delaying delivery has a considerable cost. We must move forward. I hope that the Leader of the House will let us know when we can discuss and debate this important matter.