My right honourable friend the Minister of State for Climate Change (Gregory Barker) made the following Statement.

An error has been identified in the Written Answer given to the honourable Member for Newcastle upon Tyne Central (Official Report, col. 12 February 2013, col. reference 614W). The wording was incorrect as the calculation used for the Civil Nuclear Constabulary (CNC) was per card holder rather than per member of staff, with the result that the stated CNC averages were too high.

The full answer given was as follows:

The mean average spend using a government procurement card per member of staff is as below:

| 2011 (£) | 2012(£)

DECC | 413 | 187

Coal Authority | 930 | 1,310

Committee on Climate Change | 1,405 | 1,054

Nuclear Decommissioning Authority | 360 | 250

Civil Nuclear Constabulary | 1,913 | 1,241

The correct answer using average number of staff for CNC rather than the average number of staff holding a government procurement card is:

| 2011 (£) | 2012(£)

DECC | 413 | 187

Coal Authority | 930 | 1,310

Committee on Climate Change | 1,405 | 1,054

Nuclear Decommissioning Authority | 360 | 250

Civil Nuclear Constabulary | 84 | 53

Correct Calculations:

2011:GPC spend-£87,984/1,049 (average number of staff in 2011) = £84

2012:GPC spend-£65,799/1,244 (average number of staff in 2012) = £53