Departmental Expenditure Limit (2010-11)
House of Commons, 15 February 2011, TRANSPORT.
Theresa Villiers (Conservative, Chipping Barnet)
Subject to parliamentary approval, the Office of Rail Regulation departmental expenditure limit (DEL) and annually managed expenditure (AME) will be increased as follows:
DEL: £792,000
AME: £243,000
The impact on resources and capital are as set out in the following table:
£'000
| Change | NEW DEL
| Voted | Non-voted | Voted | Non-voted | Total
Resource | 242 | 550 | 2 | 550 | 552
Of which | | | | |
Administration budget | 242 | - | 2 | - | 2
Capital | (450) | - | 350 | - | 350
Depreciation | 150 | - | (750) | - | (750)
Total | (58) | 550 | (398) | 550 | 152
The change in the resource element of DEL arises because ORR is unable to record more income than cost from the industry. £242,000 budget cover is required so that ORR can reduce the recorded negative DEL to a token vote of £2,000.
The spring supplementary also reflects ORR's cash payment £550,000 towards releasing provisions for early departures in 2010-11. ORR does not require cash to make these payments but needs to reflect the cost in non-voted DEL so that ORR does not exceed its overall DEL limit for 2010-11.
ORR needs to increase its provision due to staff changes that will take place. The spring supplementary shows a further £243,000 (non-cash) being added to a provision initially created in the main estimate. These AME costs will be recovered from the rail industry.
These changes are of a technical nature to ensure that ORR keeps within its DEL and AME limits. ORR is funded by the railway industry and anticipates an underspend against its gross budget of circa £2,000,000 this year.
Philip Hammond (Conservative, Runnymede and Weybridge)
Subject to parliamentary approval, the Department for Transport departmental expenditure limit (DEL) for 2010-11 will be decreased by £792,000 from £12,730,039,000 to £12,729,247,000.
Within the DEL change, the impact on resources and capital, are as set out in the following table:
£'000
| Change | NEW DEL
| Voted | Non-voted | Voted | Non-voted | Total
Resource | -792 | 0 | 5,941,476 | 445,810 | 6,387,286
Of which | | | | |
Administration budget | 0 | 0 | 263,948 | 2,154 | 266,102
Capital | 0 | 0 | 6,450,423 | 728,127 | 7,178,550
Depreciation(*) | 0 | 0 | -802,365 | -34,224 | -836,589
Total | -792 | 0 | 11,589,534 | 1,139,713 | 12,729,247
(*)Depreciation, which forms part of resource DEL, is excluded from the total DEL, since capital DEL includes capital spending and to include depreciation of those assets would lead to double counting.
Resource Change: Programme (total decrease of £792,000)
Voted: total net decrease of £792,000
RfRl
(i) Decrease of £792,000 by transfer to the Office of the Rail Regulation, of which £550,000 is to cover the cost of releasing provisions for early departures in 2010-11 and the remainder £242,000 to meet other costs.
Changes in Accounting Policies
Prior period adjustments.
Cost of capital charges
Costs of capital charges (CCC) have been removed from accounts, budgets and supply estimates in accordance with HM Treasury's consolidated budgeting guidance (CBG). However the Department had liabilities greater than its assets so attracted a cost of capital credit. The removal of the CCC increases resources in DEL. The prior period adjustment (PPA) in respect of the previous two years is:
| 2008-09 | 2009-10
Cost of capital credit (£'000) | 2,698,533 | 2,774,776