Beta This is a new service and it is still being tested. Tell us about a problem.

Electricity Transmission (Correction)

House of Commons, 26 January 2010, ENERGY AND CLIMATE CHANGE.

David Kidney (Labour, Stafford)

I regret that a date I gave during the Adjournment debate on electricity transmission (North Somerset) on 19 January was incorrect. National Grid's consultation on two possible route corridors for a new overhead power line from Bridgwater to Avonmouth was extended until 22 January because of the bad weather. It was not, as I wrongly suggested, extended until 22 July.

I want to make my apologies to Parliament and to the Opposition spokespeople for the error that occurred during the debate.