Queen Elizabeth II Conference Centre

House of Commons, 19 May 2009, COMMUNITIES AND LOCAL GOVERNMENT.

Iain Wright (Labour, Hartlepool)

I am today announcing key performance targets have been agreed for the Queen Elizabeth II Conference Centre for the period 1 April 2009 to 31 March 2010.

The agency's principal financial target for 2009-10 is to achieve a minimum dividend payment to the Department for Communities and Local Government equal to the total of 6 per cent. of average capital employed and a sum equal to the capital charge that applies to the building for the year concerned. The agency is currently forecasting that 2009-10 will be a year of significant challenge and that the dividend payment will be £1,000,000—a shortfall of £200,000.

An operational target has been set to achieve room occupancy within the centre of 60 per cent. of capacity. If this target is exceeded all revenues received up to a maximum of £200,000 will be added to the dividend payment of £1,000,000 thus reducing, or if trading conditions allow, eradicating the shortfall.

The Agency also has the following quality of service targets:

Overall score for value for money satisfaction of greater than 90 per cent.;

The number of complaints received to be less than two per 100 events; and

An average response time when answering complaints of less than four working days.

Return on Capital Employed

HM Treasury set an annual return on capital employed of 6 per cent. for the Centre's trading fund activities.