Rail Vehicle Accessibility (Gatwick Express Class 458 Vehicles) Exemption Order 2006
House of Lords, 2 March 2006.
Rail Vehicle Accessibility (Gatwick Express Class 458 Vehicles) Exemption Order 2006
Lord Davies of Oldham (Labour)
rose to move, That the draft order laid before the House on 7 February be approved [18th Report from the Joint Committee and 25th Report from the Merits Committee].
Lord Davies of Oldham (Labour)
My Lords, I beg to move the order confident that I shall be the only contributor to the debate because today I have such a consensual House before me with regard to transport matters. The provision of an accessible public transport system in which disabled people can have the same opportunities to travel as other members of society is a key plank in our policy to improve the lives of disabled people. We are fully aware that without accessible transport, disabled people will be limited in their ability to access work, visit friends and family, participate in leisure activities or access healthcare facilities.
That is why we have taken action to ensure that public transport services are increasingly accessible to disabled people. Our record speaks for itself. Under the Disability Discrimination Act 1995, the Secretary of State for Transport introduced accessibility regulations for rail vehicles, buses and coaches. There are already around 4,400 rail vehicles in service, which meet the Rail Vehicle Accessibility Regulations provisions in the Disability Discrimination Act 2005. That Act received support in the House last year and we are building on the achievements so far. At the time of the Act's passage, noble Lords were aware that with regard to rail services we had a perspective over almost two decades before we could complete the regeneration and refurbishment of all rail stock. Noble Lords will recognise that we have made considerable progress already. That number will double over the next 10 years and we must not forget that many thousands of older vehicles have been made more accessible during refurbishment.
As a consequence of the Act, the House has secured greater scrutiny of applications for exemptions from parts of the RVAR. We are discussing such exemptions today. The case of the Gatwick Express obtains because the operators wish to sub-lease two trains from South West Trains to provide back-up for when they have problems with their own vehicles. Gatwick Express does not expect to use these two trains for more than 70 days each year, so they are there when the usual trains for any reason are not available.
The rail vehicles which Gatwick Express proposes to sub-lease from South West Trains are similar to those currently used by that company, which is why it makes sense from an operational point of view to use that stock. Indeed, the vehicles already have similar exemptions, as they were built by the same manufacturer around the period when the RVAR was being introduced.
In general, when trains move between operators, any exemption that has been granted simply transfers to the new operator. However, a peculiarity of the exemptions system that applies to the trains that we are discussing today is that the exemptions cease if the vehicles are operated by anyone other than South West Trains. We are not discussing granting exemptions for any new items in relation to these vehicles. We are concerned simply with the transfer of existing exemptions to a different operator—namely, the Gatwick Express—and bringing the periods for those exemptions into line with those that apply to the existing fleet operated by Gatwick Express.
In accordance with the Disability Discrimination Act, we have consulted the Disabled Persons Transport Advisory Committee, the Government's statutory advisory body on transport and disability issues. The committee recognises that transferring these two trains to Gatwick Express would deliver benefits to disabled people. The trains that were previously used as back-up were built way back in the 1970s and have very poor provision for disabled passengers. The trains to be transferred are better equipped for the disabled, but they are not fully compliant with the regulations and the Act. That is why an exemption order is necessary.
Given the very limited use of the vehicles in question—they are to be used as substitutes only when the other vehicles are not able to be used—and the support of the Disabled Persons Transport Advisory Committee, the Government believe that this is a reasonable application. I beg to move.
Moved, That the draft order laid before the House on 7 February be approved [18th Report from the Joint Committee and 25th Report from the Merits Committee]—(Lord Davies of Oldham.)
Lord Hanningfield (Conservative)
My Lords, I might surprise the Minister by asking a question on this order. We in no way oppose the Gatwick Express exemption order, but the Minister said that it might take two decades to make all carriages comply with the Act. Will many of the carriages be converted towards the end of the two decades? One would obviously be unhappy if considerable progress towards compliance with the Act was not being made during the whole period.
Lord Snape (Labour)
My Lords, I declare an interest as an employee of the National Express Group, the parent company which will eventually operate the class 458 trains, subject to this affirmative order. The Minister's emollient phraseology nearly tempted me not to intervene at all. He dealt with the previous order with his typical concern and adequacy, and the House obviously accepted everything that he said, as did I.
However, emollient though he might have been on this matter, I draw one or two items of concern to his attention and seek one or two assurances, on behalf not just of the Gatwick Express train operating company but also other train operating companies which might find themselves in the similar position of wishing to sub-lease fairly modern rolling stock in future.
I remind the Minister and the House that the trains to which we are referring are caught under the terms of this legislation because they were delivered late to the original train operating company, South West Trains. They were designed prior to 1999, before the regulations came into being. We are discussing today a comparatively minor series of necessary alterations to the trains to make them comply with the Disability Discrimination Act.
What my noble friend did not tell the House—there is, perhaps, no reason why he should, but I certainly intend to—is that this matter has been dragging on for some considerable time. These two trains—which, as the Minister rightly says, are not in daily service, but used as back-up—have been sitting in the Stewarts Lane railway depot for the past six months, waiting for this House and the Department for Transport to pass this affirmative resolution. I happen to think that such a procedure is nonsensical to say the least. Had the Gatwick Express train company never bothered to introduce back-up trains, it could have carried on using the mark 2 rolling stock with slam doors electrically hauled or propelled, none of which would have been affected by these particular regulations, because those trains were introduced into service a long time before 1999. The fact that the train operating company behaved in the way it did, and sought to sub-lease these vehicles, means, as I have indicated, that until your noble Lordships' House has gone through this affirmative procedure, the trains will sit in a siding at Stewarts Lane.
I do not know whether your Lordships feel that is a sensible way of doing things, but I do not and I do not know anyone connected to the railway industry who does. In opening the debate, my noble friend talked about the work this Government have done to make life better for disabled people. I support and applaud that. But we are talking here about a number of comparatively minor alterations needed to fairly modern rolling stock, none of which amounts to a hill of beans. They would all be quite expensive if done just for two trains out of the total fleet of class 458 trains, but none of them is particularly serious. For example, we are talking—as we did last time exemptions were sought for similar rolling stock—about the internal display being only 31 millimetres high, instead of 35 millimetres high, as laid down by the regulations.
I repeat: these trains were designed prior to the regulations appearing in the first place. We are not talking about an unthinking or uncaring government or train operating company introducing rolling stock that is totally unfit for use by disabled people. These are comparatively minor things, such as the additional pressure needed to open internal doors, and the redesign necessary to the toilets in order that people can leave a wheelchair, use the toilet and return to the wheelchair. These are significant, but scarcely earth shattering matters, but for six months these trains have lain in a siding, waiting for your noble Lordships to pass this particular procedure.
According to the explanatory memorandum, this is the first such order to be subject to draft affirmative resolution. I know the Department for Transport is currently developing draft regulations and expects to consult later this year. I understand that, until regulations are in force, all exemption orders remain subject to draft affirmative resolution procedure. My first question to my noble friend is: why have we had to wait so long for the opportunity to debate this matter?
Secondly, how long will this exemption last? My noble friend indicated that the Gatwick Express Company's existing franchise will last until 2011. Immediately, there are two points to consider here. First, these trains are off-lease in February 2007, when the original lease granted to South West Trains expires. Do we need, some time after that date, to adopt this procedure all over again? If that is the case, does my noble friend think that is a sensible way of going about things? Can he give us an assurance today that these trains will not spend another six months in the Stewarts Lane sidings, while the business managers of your noble Lordships' House decide whether to put on a similar order in future?
I remind my noble friend that the future of the Gatwick Express TOC is by no means assured. There is a feeling, which was first expressed by the now defunct SRA, that having these trains, modern though they may be, passing non-stop from Victoria to Gatwick Airport, clogs up the former southern main line. At various times of the day, when commuters are standing at various stations waiting to get to and from the city, these trains pass with lots of empty seats. There is a move afoot to extend the train route at least as far as Three Bridges, which would of course mean considerable changes to the existing TOC—and, in the opinion of most of the railway press, the abolition of the Gatwick Express TOC. I presume, though my noble friend may correct me if I am wrong, that that would mean yet another affirmative order for whoever picks up those trains to use as back-up. I have not been here long enough to know who is responsible for the business in your Lordships' House, but it sounds as if he or she will be fairly busy in the months and years to come, arranging affirmative legislation, if that is how we are to proceed, to take care of all these anomalies.
I would be grateful—and I suspect that many who take an interest in these matters outside the House would be grateful—for some clarification. Basically, why has it taken so long to debate this matter? How long will the exemption actually last—until 2007 or 2011? Bearing in mind that the nature of the Gatwick Express is likely to change fairly dramatically, do we need further affirmative legislation to keep these trains in service? Would my noble friend agree that the whole exercise has not really commended itself to the railway fraternity at large?
In closing, I suggest that when we look at how these matters are decided in future, while understandably concerning ourselves with the rights and abilities of people with disabilities to use railway rolling stock, we reflect that what we have created is a bureaucratic nightmare. We have, and are likely to continue to have, lots of modern trains up and down the country that are not in service and not carrying passengers but are waiting for your Lordships to pass some sort of affirmative legislation. Perhaps my noble friend can think some more verses to the old Flanders and Swann song, along the lines of, "It all makes work for the bureaucrats to do".
Lord Addington (Liberal Democrat)
My Lords, the last speech was interesting. I agreed with some of it in that we have all had to wait far too long to pass something that might improve the situation. These vehicles are nowhere near as disabled-unfriendly or far below the standards we have set as their predecessor. So I support the noble Lord, Lord Snape, in saying that we have waited for far too long to get a better back-up in place. However, I am afraid that he downplayed the fact that these are minimum standards that we have set and the Government are required to give us a reason why they are not imposing those minimums on the rolling stock that is being used.
Even if we are talking about comparatively small changes in the scheme, in percentage terms, it may happen that your arms are not quite strong enough to use the door at this level, or not to use it consistently. On a comparatively short journey, it may not happen, but if you have to use the doors three or four times and you have very little strength in your muscles due to various conditions, you are then stranded within a loo. That is not a good situation and it will be inconvenient to everyone else. Can the Minister agree that we should ensure that the standard is enforced and that those who do not come up to it should have to jump through a few hoops to get there? Having said that, if they are prepared to jump, let us make sure that they do it quickly. I think that that is probably a fair compromise.
There has been a history between myself and the Minister in trying to get these regulations in place. I initially complained about the same line, quite a while ago, when we set this hare running—which ended up with greater responsibilities on Parliament for the amount of reporting in place, as a result of the upgrading of the Disability Discrimination Act 1995. I thank the Minister for the work that he did on that. I hope the Minister will confirm that the Government take exemptions from standards seriously. It is not something that should become almost automatic; before we raised this, there was a grave danger that it would. Will the Government make sure that we always address this seriously in future?
So, returning to the fact of the matter, this is a comparatively small change, but every change here which potentially imposes on the dignity and, indeed, the practicality of a disabled person travelling should be taken seriously and scrutinised by Parliament. It should be done as quickly as possible to ensure that we can raise standards overall, even if in smaller steps than I would like. Having said that, I have no major objection to this legislation.
Lord Bradshaw (Liberal Democrat)
My Lords, I am quite horrified at the size of the documentation and the amount of effort that has clearly gone into the process of approving the use of two other trains to replace those which are being taken out of service. The Government frequently say that they want to reduce bureaucracy but this example is absolutely scandalous. Someone has spent a lot of time working on this.
The sets of trains which have been put onto the Gatwick Express are, as far as I understand it, the best available. While matters such as windows not being in order and whether doors open properly are relatively small, one should be able to deal with them immediately without requiring the publication of large documents. In all honesty, that sort of fault can happen on the best stock—but it should be dealt with. We should not really be holding up a train operating company from introducing better rolling stock while such documents are produced. I am concerned that we may have many of these documents, at great expense, unless we find a fairly simple and standard way of moving trains round from one part of the country to another. This situation will increasingly happen as a lot of rolling stock comes off its lease and is available for transfer.
Lord Davies of Oldham (Labour)
My Lords, the House will not expect me to take quite the pessimistic view that the noble Lord, Lord Bradshaw, takes on the issue. I want to reassure him that we are concerned to introduce a framework for the orders, after consultation, in which we can minimise the amount of valuable time in which the House needs to be occupied by the orders and the demands of their necessary documentation. I give him reassurance that we are addressing that issue.
The noble Lord, Lord Hanningfield, asked me the major question in his characteristic way in terms that I was readily able to comprehend and answer. I am not so confident that I am able to follow my noble friend Lord Snape down the intricacies of his contribution. The noble Lord, Lord Hanningfield, will know that we take some pride in having 4,400 vehicles compliant with the Act. We see that in the construction of all new vehicles that they are inevitably obliged to comply with the Act, while as other vehicles come in for refurbishment they too are obliged to become compliant with it. So we expect the number of vehicles becoming compliant to double over the next 10 years.
The noble Lord, Lord Hanningfield, will know that on the deadline that the noble Lord, Lord Addington, and I debated at considerable length during passage of the Bill—when, I must add, the Conservative Front Bench also played its part—we undertook that all railway vehicles would be compliant by 1 January 2020. I recall the Liberal Democrat spokesman being particularly keen for it to be done four years early—but then they are conspicuous spenders of both public and private resources on these matters. Whether the Conservative Front Bench was equally profligate on that occasion I cannot now recall, so I shall not accuse the noble Lord, Lord Hanningfield, of that. Certainly he was not at that time in his place with regard to the legislation. So 1 January 2020 is our end date for full compliance.
Therefore, I must address what is really a debate between the noble Lord, Lord Addington, with his keen and proper advocacy of the needs of the disabled and for as many vehicles as possible to be compliant, and my noble friend Lord Snape, who indicated the difficulties for the industry—with which I have some sympathy. The noble Lord, Lord Addington, is right in that any departure from the requirements of the Act and the regulations marginally—perhaps only marginally—disadvantage the disabled. I reassure the noble Lord that what the noble Lord, Lord Snape, said was right; the kind of deficiencies on the two trains that would be deployed on the Gatwick Express are marginal.
My noble friend Lord Snape indicated that one of the weaknesses is that the internal visual announcements are smaller than required—we specify not less than 35 millimetres high and they are only 32 millimetres high. The internal door controls are not illuminated; there is no illumination of steps; the handrails of external doors are not positioned as required; and some of the door controls are not positioned at the regulated height. All of those are factors that disabled people may well struggle with and we want disabled people to be able to use these trains like any other passenger.
So there is an element of providing dispensation, but I emphasise to the noble Lord, Lord Addington, that my noble friend Lord Snape is right—that this is on the margin of inconvenience and that these are substitute trains. They come into play only when the Gatwick Express is not able fully to meet demand due to difficulties with its other trains.
My noble friend Lord Snape asked me about some larger issues. First, he berated me for the time it has taken to produce the order. I seem to recall that in a previous life he had some responsibility for the organisation of parliamentary business in the other place. Whether he used to originate that business or merely process it, I cannot recall, but as a Whip he would have taken a keen interest in how we organised parliamentary business. He knows that it is not easy to find time for regulations. We have to work within the framework of the limited time that we have available and I can tell the noble Lord that we would have liked to have dealt with the order earlier, but we have to join our place in the queue. He will also recognise that we had to undertake significant consultation. As I told the noble Lord, Lord Bradshaw, we want to establish a framework which will not mean a huge amount of work either for those seeking to comply with the regulations or for ourselves in seeking to enforce them and in processing them through this House and another place.
We want to obtain regularity on this issue so that it does not become an excessive burden on all concerned. But my noble friend will recognise that we have a fair bit of work to do on this. The easier part is applying the regulations to new build. That is obvious enough, although, as my noble friend will be aware, that is not always the easiest exercise and consumes an enormous amount of experts' time.
If we are to tackle these issues effectively, we need time to get the orders right. I accept my noble friend's main thrust—that this order has been some time coming. It is therefore inconvenient to the operators. We need a structure to deal with this issue in future, because there will be other necessary exemptions. The noble Lord, Lord Bradshaw, is also right: there will be movement of trains. It is bound to decrease over time because all new build is compliant and operators are not neglectful of the Act and the requirements. Where they can, they will effect the necessary changes as time goes on.
We will therefore have a steady rate of progress. But I accept the comments of my noble friend Lord Snape that these things need to be addressed in a forthright manner and we need to make as rapid progress as we can. I am aware of the points that he makes—that train operators want to be compliant with the Act and will do their best and that all new build will be certain to meet these requirements. In seeking to do that train operators have a challenging time ahead. With certain trains there is quite a lot of work to be done and, as the noble Lord, Lord Bradshaw, indicated, it raises the issue of exemptions when trains are moved round the country.
I would like to convey to the noble Lords, Lord Bradshaw and Lord Snape, that we are fully cognisant of that issue. Both are well versed in the issues of the rail industry and they will know that it is not in the Government's interests to put undue burdens on train operators. But, equally clearly—and I would like to reassure the noble Lord, Lord Addington, on this front—there is no way in which this Government would in any way, shape or form resile from the obligations under the Disability Discrimination Act 2005 which we are proud to have passed. We recognise the achievements of the original Act under the previous administration in 1995. We want as many rail vehicles as posible to be fully compliant as soon as possible.