Olympic Games 2012: Olympic Park Master Plan
House of Lords, 30 January 2006.
Lord Davies of Oldham (Labour)
My right honourable friend the Secretary of State for Culture, Media and Sport (Tessa Jowell) has made the following Written Ministerial Statement.
The master plan for the Olympic Park was largely developed in the second half of 2003 by the EDAW consortium and outline planning permissions were secured in autumn 2004. The candidate file submitted to the International Olympic Committee (IOC) in November 2004 and subsequently presented to the Evaluation Commission in February 2005 presented the concept of a compact Games with the Olympic Park at its heart.
Since winning the right to stage the Olympic Games and Paralympic Games on 6 July 2005, the master plan has been reviewed, as part of the normal development process for a major project. This review has resulted in changes that will deliver a more compact Olympic Park, while meeting the technical specifications of the IOC. In summary, the revised master plan will:
free up some land that previously had been required for the Olympic Park;
avoid the relocation of about 100 businesses, more than 70 homes and a place of worship, and safeguard more than 1200 jobs;
reduce overall programme and delivery risk;
enhance operational security, needed after the terrorist attacks on 7 July 2005; and
be delivered with a potential cost reduction over current estimates of between £250 million and £350 million.
A detailed review has been undertaken of the Olympic village and the core Olympic and Paralympic requirements to improve deliverability, efficiency of design, utilisation, reduce risk and costs and smooth the way for best legacy use.
The revised plan therefore proposes realigning the village to locate approximately 80 per cent of it on the Stratford rail lands immediately to the north of the Channel Tunnel Rail Link (CTRL).
The proposed building envelope and mix of uses complies with Stratford City's existing planning permissions and will provide a village of a similar high standard to that proposed in the original master plan.
This move will enable an earlier start on the village, allowing building work on almost half of it to begin before power lines have been placed underground.
The revised plan is intended to offer improved security through:
the relocation of the IBC and MPC within the Olympic Park security cordon, bringing those facilities closer to the centre of the Olympic Park and away from major roads and unsecured car parks;
integrated security measures for Stratford City and the Olympic Games should enable the concurrent construction of the projects to progress more efficiently; and
a more compact athletes village should improve the efficiency of the security operation.
Further work on refining and developing the security aspects of the revised plan is in hand.
Details of the revisions to the master plan are set out in maps to be placed in the Library of the House.
The overall cost reductions for land, remediation, relocation and demolition are £152 million of which £142 million relates to the LDA and £10 million for demolition relates to the ODA as analysed below:
| | £ million
Land assembly, relocation and remediation
LDA | Fish Island/car parking
(Relocation of majority of 53 businesses, 72 homes avoided and 621 jobs safeguarded) | 66
LDA | IBC/MPC relocation
(Relocation of 42 businesses and 642 jobs expected to be safeguarded) | 76
Demolition
ODA | Fish Island/car parking | 4
ODA | IBC/MPC relocation | 6
| | 152
In addition, reductions in other ODA costs of between £100 million and £200 million, compared to the current estimated cost for the original master plan, are estimated to be achieved. These savings will mainly be achieved through:
reduced costs for the construction of the IBC/MPC; and
the relocation of car parking from Fish Island, with 2,000 vehicle spaces being provided in Stratford City multi-storey parking and a smaller temporary multi-storey car park on the Pudding Mill site replacing the need for a large multi-storey car park at Fish Island.
The actual savings will be dependent on the outcome of the commercial deal to be negotiated with Stratford City and further value engineering that will be undertaken as part of the detailed design work.