Beta This is a new service and it is still being tested. Tell us about a problem.

South Hampshire Rapid Transit Scheme

House of Lords, 29 November 2005.

Lord Davies of Oldham (Labour)

My honourable friend the Parliamentary Under-Secretary of State for Transport (Derek Twigg) has made the following Ministerial Statement.

In July 2004, I took the decision to withdraw funding for the South Hampshire Rapid Transit (SHRT) scheme because of excessive cost increases. Since then, the scheme's promoters, Portsmouth City Council and Hampshire County Council, have put revised proposals to the department.

I have considered very carefully all the new information provided by the promoters. The promoters have succeeded in reducing the cost of the tram schemes below last summer's level. However, costs remain significantly higher than those the department approved.

The latest tram proposals are still very expensive—costs are nearly 50 per cent higher than originally planned. This is for a reduced scheme which places more of the risks with the public sector. I therefore cannot support requests to re-instate the SHRT proposal.

The scheme was given full approval in 2001 with a cap on the public sector funding of £170 million, present value terms at 2003 prices. Following receipt of bids that greatly exceeded the approved public sector cost, the promoters put forward an alternative proposal in late 2003 removing the proposed cycle shuttle and introducing revenue risk sharing. But the public sector funding remained £100 million more than we had approved.

The promoters' latest proposal requires public sector funding of £214 million in 2003 present value terms. Cost savings were achieved by removing the short loop proposed for Fareham and changing the proposed procurement, with less risk transfer to the private sector. This is a 26 per cent increase above the previously approved amount. However, this simple comparison does not give a full picture because:

These figures are the total value in 2003 of the required public funding, at 2003 prices. In 2005, at current prices, the value would be £253 million—nearly 50 per cent above the approved cap. And this is still a present value figure, so it understates the cost increase in cash terms over the life of the scheme.

But it is the cash costs that count. The current proposal would require £93 million of capital grant and a total of £581 million in annual payments, associated with the PFI credits, up to 2036. The original proposal required grant of £75 million, and £244 million in annual payments to 2033. The cost to government has therefore more than doubled, from £319 million to £674 million, over 36 years.

I appreciate that the promoters have made every effort to reduce the costs of the scheme. However, it is clear that costs remain significantly higher than those that I previously approved. In the light of all the information, I cannot support requests to re-instate the SHRT proposal.