A303 Trunk Road (Stonehenge)

House of Commons, 20 July 2005, TRANSPORT.

Stephen Ladyman (Labour, South Thanet)

Plans to upgrade the A303 trunk road passing Stonehenge and to improve the setting of this outstanding World Heritage Site have a long history. In July 1998, after extensive assessment of alternative options, the Government announced the inclusion in the targeted programme of trunk road improvements of the A303 Stonehenge improvement as an "exceptional environmental scheme". Following further studies and consultations, a preferred route was announced in June 1999 for improvements to 12.4 km of the A303 running from the countess roundabout in the east to Berwick Downs in the West. The scheme provided for dualling of the route and included a bypass of the village of Winterbourne Stoke and a 2km cut-and-cover tunnel past Stonehenge.

Following further consultations with English Heritage and the National Trust, a number of alternative tunnel options were evaluated and on 10 December 2002 the Government announced that they would proceed with further consideration of a 2.1 km tunnel (extending the tunnel by 100 metres compared with the preferred route announcement) and that the tunnel would be bored rather than cut-and-cover, thereby providing significant additional environmental benefits.

The public inquiry into this proposed scheme was held between 17 February and 11 May 2004. The inspector's report was received in January 2005 and the Government have been considering it carefully. The inspector, having considered all the representations and submissions from objectors, was satisfied that the case for the scheme had been made and has recommended that the scheme orders should be made, subject to a number of minor modifications. In particular, he was satisfied with:

the line of the published scheme;

all the proposed slip and side road changes required to implement the scheme;

the requirements of the traffic prohibition orders restricting certain classes of traffic from using the tunnel and some of the new roads; and

the acquisition of all the land and interests necessary to carry out the published scheme.

However, there has been a material change in the estimated scheme costs since the scheme went to public inquiry and which was not part of the inspector's considerations. The Highways Agency's evidence to the public inquiry indicated that the construction cost of the scheme would be £192 million. After allowing for additional factors including land, preparation and supervision costs this translates into a total outturn scheme cost of £284 million, assuming a construction start date of spring 2005.

In addition, following the completion of the public inquiry, the Highways Agency has carried out further detailed assessments of the ground conditions through which the tunnel would be bored. These have confirmed the scale of two significant factors along the line of the proposed tunnel:

very large quantities of phosphatic (soft, weak) chalk;

a high water table, with the groundwater potentially rising to the surface at times of heavy rainfall where the tunnel passes below a shallow valley to the south of Stonehenge.

These factors would significantly complicate the tunnelling process and extend the overall construction period of the scheme. Together with certain other factors which serve to increase tunnel costs, including more rapid increases in construction cost inflation than had previously been anticipated, the Highways Agency's latest estimate of the outturn cost of the scheme has now risen to some £470 million. For consistency with earlier estimates, this figure also assumes a construction start date of spring 2005. Slippage in the start date beyond spring 2005 will have further increased the estimated cost in line with continuing inflation in construction costs.

This represents a significant change to the basis on which the Government originally decided to progress this scheme. Our recognition of the importance of Stonehenge as a World Heritage Site remains unchanged but given the scale of the cost increase we have to re-examine whether the scheme still represents value for money and the best option for delivering improvements to the A303 and the setting of Stonehenge. The Government therefore plan to carry out a detailed review of the options, consulting relevant environmental interests including, in particular, English Heritage and the National Trust, before taking a final decision on the inspector's report. The review will also consider the implications of delaying the Stonehenge scheme for the delivery of improvements proposed for other single carriageway sections of the A303 further to the west.

I have placed copies of the inspector's report in the Library of the House.