Manchester Metrolink
House of Commons, 16 December 2004, TRANSPORT.
Alistair Darling (Labour, Edinburgh Central)
In July this year I told Parliament that because of excessive cost increases I would have to withdraw funding for the phase III extensions to Manchester Metrolink.
Looking at the proposals, it has become increasingly clear there are real and persistent problems with the costs of the extensions. The public sector funding requirement has almost tripled since we first approved the project. Nevertheless, I have decided to commit over half a billion pounds, the sum previously agreed to fund phase III, to Manchester's transport network. Manchester will also be able to bid for additional funds from the new transport innovation fund. It is now up to the transport authority to come forward with proposals for how this funding is used.
Looking at the history of the Metrolink proposals shows the problems it has had with huge increases in public funding requirements:
In July 2000 public sector funding was approved with an up front budget of £282 million, for three lines: to Oldham and Rochdale, Ashton and the airport; plus some upgrading of the existing system.
In December 2002, this budget had to be increased to £520 million (including £60 million local contribution). We made clear that there would be no more money from the Department. The Manchester authorities accepted they would meet the costs of any further increases.
In December 2003, GMPTE returned to ask us for still more money, but for a reduced project. The three new lines were reduced to two and a half, with the line to the airport replaced with a shorter spur to East Didsbury.
The public sector funding requirement was going up and up—partly because of private sector, pessimism about light rail, and partly because of failings in the original cost estimates. There was no guarantee that costs would not continue to rise. This led to my decision last July to withdraw funding for this project, and to ask GMPTE to work with us to look at alternatives that would benefit Manchester, but at a better price.
Following this decision, a working group was set up with GMPTE and chaired by Tony McNulty. Its purpose was to see whether light rail could be made affordable in Manchester and to consider alternatives. I also appointed my own financial and technical consultants.
The potential cost to taxpayers of the proposed extensions is now clearer:
GMPTE confirm that at least £600 million public sector up front funding would be needed to build just two lines—Oldham-Rochdale and Ashton. Our judgement is that there is a strong chance that costs would be even higher.
GMPTE told Tony McNulty on 7 December that about £900 million of up front funding would be needed for delivery of the original three lines over the next 10 years—a tripling since the original approval. There is no guarantee this would not increase further.
In the light of this, I have considered the options for the way forward. GMPTE want me to agree to their continuing with their current procurement for the three lines. That would mean committing to upfront public sector funding of £900 million, when only four years ago we capped the figure at £282 million. I cannot do that. No Government could ignore these huge increases—a three-fold increase in just four years. And accepting this price would consume too much of the money that will be available for transport including in the north-west in future years. In addition, a scheme for substantially less than three lines would need a new procurement or risk legal challenge. I have therefore told GMPTE that the current procurement should not be revived.
Nor can I agree to GMPTE's alternative of starting a new procurement to enable construction of the three lines to be phased over a longer period. This would not address the fundamental problem of cost escalation.
I am however confirming that the £520 million budget is still available for Manchester, subject to GMPTE developing a satisfactory plan for these areas. This represents a major investment in Manchester, enabling a package of measures to address the transport problems in these parts of the city, which may include light rail improvements.
We have already provided some £170 million of the £520 million. Around £80 million was for GMPTE to buy the concession for the operation of Metrolink. This has continuing value to generate revenue for GMPTE and give them greater control over the tram network. The rest has been for advance works and buying land, some of which may still be required for the package that GMPTE now develop.
GMPTE are able to supplement this budget, both from their own resources and by bidding for funding from government through the transport innovation fund. The TIP is available for authorities which propose innovative and coherent schemes to tackle congestion and encourage modal shift which could act as exemplars for others facing similar challenges. This provides a real opportunity for Manchester to look at its transport policy across the piece and develop a bold integrated package.
The budget I am committing today provides the opportunity for a major transport investment package for these areas of Manchester. It is now up to the Manchester authorities to make the most of this opportunity, and to come forward with proposals that will deliver the transport improvements that these areas need.