Highways Agency Development Control Policy

House of Commons, 27 October 2004, TRANSPORT.

Tony McNulty (Labour, Harrow East)

This statement supplements Roads Circular 4/2001: "Control of Development Affecting Trunk Roads and Agreements with Developers under Section 278 of the Highways Act 1980".

Review of Policy

The Department for Transport, Office of the Deputy Prime Minister and the Highways Agency have been carrying out a review of the existing development control policy to see if there are any measures that could be introduced to speed up development where possible. As a result of this work the Highways Agency proposes to implement the measures outlined below.

Development in Advance of Completion of Road Improvement

The Highways Agency has considered and agreed to allow, where possible and at the request of the developer, all development to go ahead in parallel with any road infrastructure improvements being carried out under an s278 agreement. This will be subject to safety considerations and on the understanding that the Highways Agency cannot be held accountable for any delays to the road works or resulting delays for the developer.

This change would mean that developers could access sites earlier, start work and have, for example, houses ready for immediate occupation as soon as the road infrastructure was completed.

Increased use of Trigger Points

In addition, the Highways Agency has agreed to consider the use of "trigger points" so that where there is any surplus capacity in an existing network developers could utilise that capacity in their proposals. This means that developers will be allowed to proceed with their development up to an agreed point, a point where the traffic generation matches the reserve capacity. This point will usually be assessed on a given floor area for an industrial development or a specified number and size of houses for a housing development.

This change means that, where there is any surplus capacity in an existing network, developers will be able to complete and have occupied specified parts of a proposed development in advance of any network improvements required under an s278 agreement.

Time scale

These changes to the existing development control policy will be implemented with immediate effect.